England Cases

There are over 300 English cases in our database. This page shows all the cases by default, but you can filter the list by using the search tool above. You can search within the title, key terms, court name, judge's name and case notes fields by inputting a word, or words, or part of a word, or a phrase, into the search box.

  • 9th November 2000
    Canary Riverside Development v Timtec International [2000] R.Ct of Justice 69/2000
    This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes   Where a party seeks leave to bring adjudication proceedings but litigation has already been commenced against that party then leave may be refused where the subject matter of an adjudication is capable of being resolved by way of a defence and counterclaim to the litigation. Each case will depend on its own facts. Deputy Judge: Mr DKR Oliver QC, Royal Courts of Justice 9 November 2000 CRD engaged TI under a trade contract to carry out works on a riverside development. The procurement was by way of construction management. TI made 2 applications for payment under the Trade Contract for a sum totalling £285,300.44. CRD prepared and signed a cheque for that amount. CRD subsequently discovered that TI had gone into administration 2 days...
  • 16th October 2000
    Maymac Environmental Services v Faraday [2001] 75 Con LRHT 00/222
    This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes Any points to be made about whether the adjudicator has jurisdiction to act should be made during the adjudication itself, otherwise the parties are likely to be found to have consented to the adjudication process and will be estopped from arguing the adjudicator had no jurisdiction in any enforcement proceedings. HHJ Toulmin QC, Technology and Construction Court 16 October 2000 M was a mechanical and electrical sub-contractor to F and applied for payment for works done. M only received part of the payment and so referred the payment dispute to adjudication under HGCRA 1996 and the Scheme. The adjudicator awarded the sum claimed by M plus interest. F refused to pay. M applied for summary judgement to enforce the adjudicator's decision in its favour. F...
  • 2nd October 2000
    Woods Hardwick Ltd v Chiltern Air Conditioning Ltd HT 00/28
    This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes If there are significant departures from the Scheme's rules, the Court will not enforce the adjudicator's decision. Adjudicators should take care if they provide evidence for use in enforcement proceedings. A proper abatement is outside Section 111 and a notice to withhold is not required. HHJ Thornton QC, Technology and Construction Court 2 October 2000 W applied to enforce 2 adjudicator's decisions (from 2 different contracts) against C. For the first decision, C argued that the judgment should be stayed pending the trial of its action against W arising from another unrelated contract. The Court held that this was no reason to hold up payment of the adjudicator's award, and awarded judgment. C challenged the decision in the second adjudication...
  • 7th September 2000
    Cygnet Healthcare plc v Higgins City Ltd [2000] EWHC 00/285 (TCC)
  • 30th August 2000
    Elanay Contracts Ltd v The Vestry [2000] HT 00264
    This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes Adjudication is not subject to Article 6 of the European Convention on Human Rights because it does not involve a final determination of civil rights. HHJ Richard Havery QC, Technology and Construction Court 30 August 2000 E applied to enforce an adjudicator's award by summary judgment. However, it served a fully pleaded Particulars of Claim, including reference to terms of the contract. V served a Defence and Counterclaim. V also opposed the application for summary judgment. V's first argument was that if summary judgment was awarded, it would be estopped from relying upon issues raised in the Defence and Counterclaim in future proceedings. The Judge held that this was incorrect, on the basis that if there was to be an issue estoppel, the particular...
  • 24th August 2000
    Universal Music Operations Ltd v Flairnote Ltd [2000] HTT-00-224
    This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes In a project management contract, the project manager is merely acting as agent for the employer, so any contract made between the project manager and a contractor is deemed to be a construction contract within Part II of the HGCRA 1996 between the employer and the contractor. Wilcox J, Technology and Construction Court 24 August 2000 U owned a number of properties in London, and had used S as project managers when undertaking work on the properties. They used a contract described as an agreement for project management and management contracting services which provided for S to arrange execution of the contract by the contractor. A project was planned to refurbish a building in Chelsea. A draft agreement was discussed between U and S based on the...
  • 9th August 2000
    Discain Project Services Ltd v Opecprime Developments Ltd No1 [2000] BLR 402 (TCC)
    This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes An adjudicator can decide that a dispute has arisen, even if the due date for payment has not arrived. The Court may not enforce the adjudicator's award if the manner in which it has been reached breaches the rules of natural justice. HHJ Bowsher QC, Technology & Construction Court 9 August 2000 A dispute arose between the parties, and an adjudicator was appointed. The Scheme for Construction Contracts applied in the absence of any adjudication provisions in the contract. The adjudicator awarded sums to D, but O did not pay. D therefore applied for summary judgment of the sum awarded. O challenged the jurisdiction of the adjudicator, and raised arguments relating to natural justice. Firstly, O said the notice of adjudication was premature,...
  • 9th August 2000
    Whiteways Contractors (Sussex) Ltd v Impresa Castelli Construction Ltd [2000] EWHC Technology 67
    This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes Although the adjudicator under certain contracts has no power to determine his jurisdiction, the parties may decide between themselves to extend his jurisdiction. In applying sections 110 and 111 of the HGCRA, there is no distinction to be made between set-off and abatement. HHJ Bowsher QC, Technology and Construction Court 9 August 2000 W was a plastering sub-contractor who was engaged by I in connection with a construction in London. The contract incorporated the terms of the standard form of contract for sub-contractors DOM/1. Article 3 and Clause 38 of those terms provide for disputes or differences between the parties to be referred to adjudication. W gave its notice to adjudicate by letter dated 13 January 2000. The adjudicator gave his decision...
  • 1st August 2000
    ABB Power v Norwest Holst Engineering Ltd [2000] EWHC Technology 68
    This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes Section 105(2) of HGCRA construed quite broadly using a purposive approach to decide if any given contract constitutes an exempted construction operation. In this case, a contract to install insulation to clad pipework etc on a site where the primary activity was power generation was outside the scope of the Act. HHJ Humphrey LLoyd QC, Technology and Construction Court 1 August 2000 ABB placed an order with N to install insulation to clad pipework, drums and various other parts of the equipment at a site where ABB was building three new heat recovery steam generators (HRSGs) as part of a project to extend an existing power station. N was also to pre-fabricate the cladding material. There was a dispute about payment and N gave notice of adjudication...
  • 31st July 2000
    Bouygues UK Ltd v Dahl-Jensen UK Ltd [2000] EWCA Civ 507
    This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes Where one party is insolvent and the parties have claims against each other, summary judgment is not appropriate. The operation of rule 4.90 of the Insolvency Rules means that there is a real reason to dispose of the claims at trial. Court of Appeal (Peter Gibson, Chadwick and Buxton LJJ) 31 July 2000 The facts and decision at first instance are set out on page 14. B appealed from the decision of Dyson J on the ground that the adjudicator had decided a matter outside of his terms of reference. The Court dismissed B's appeal. The Court recognised that the purpose of section 108 of HGCRA 1996 was to provide parties with a speedy method of resolving disputes, which although not finally determinative, could be sued upon. Where an adjudicator had answered...