Beckhaus v Brewarrina Council [2002] NSWSC 960

Contracts - Building, Engineering and related contracts.
Summary judgment application in respect of a progress claim under CL42.1 of AS 2124-1992. Superintendent fails to deal with claims within time. Contractor fails to supply statutory declaration as to payment of subcontractor. Held amount of progress claim due. - Progress claim also made under the Building Construction Industry Security of Payment Act 1999. Held claim under statutory scheme and under contract can be made at same time in one document.