Thiess Pty Ltd & Anor v Lane Cove Tunnel Nominee Company Pty Ltd & Anor [2009] NSWCA 53

Contracts - construction contract - Building and Construction Industry Security of Payment Act 1999 - payment schedule - whether contract required a time for provision of payment schedule - contractual payment schedule replied to contractual progress payment claim - not to statutory payment claim - stated time was not for provision of statutory payment schedule.