- Home
- Nomination
- UK Cases
- Overseas Cases
- Panel
- Guidance
- Glossary
- Legislation
- England & Wales
- Wales
- Scotland
- Northern Ireland
- Australia (Australian Capital Territory)
- Australia (New South Wales)
- Australia (Northern Territory)
- Australia (Queensland)
- Australia (Southern Territory)
- Australia (Tasmania)
- Australia (Victoria)
- Australia (Western Australia)
- Eire
- Isle of Man
- Malaysia
- New Zealand
- Singapore
- Links
- Contact Us
Gemini Nominees Pty Ltd v Queensland Property Partners Ltd ATF The Keith Batt Family Trust [2007] QSC 20
BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION –STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – where builder and owner entered into a written cost plus contract for renovation works to house property – where payment claim served by builder under Building and Construction Industry Payments Act 2004 (Qld) – where owner did not serve payment schedule – where no fair and reasonable estimate of total amount builder was likely to receive under the contract was given to owner pursuant to s 55 Domestic Building Contracts Act 2000 (Qld) – whether contract that is unenforceable under s 55(3) Domestic Building Contracts Act 2000 (Qld) is a contract to which Building and Construction Industry Payments Act 2004 (Qld) applies