Hitachi Ltd v O'Donnell Griffin Pty Ltd & Ors; O'Donnell Griffin Pty Ltd v Hitachi Ltd & Ors [2008] QSC 135

ADMINISTRATIVE LAW – JUDICIAL REVIEW – REVIEWABLE DECISIONS AND CONDUCT – REVIEW OF PARTICULAR DECISIONS – adjudication of progress payments under the Building and Construction Industry Payments Act 2004 (Payments Act) – where adjudication considered selected larger variation claims but not numerous small claims – where applicant/respondent sought an order that adjudication decision was void – whether having regard to legislative intent, s 26 Payments Act requires an adjudicator to examine each and every variation in a large claim – whether the adjudicator acted bona fides – whether the adjudicator observed procedural fairness