MPM Constructions v Trepcha Constructions [2004] NSWSC 103
BUILDING AND CONSTRUCTION - Building and Construction Industry Security of Payment Act 1999 - progress payment - adjudication application - adjudication determination made out of time - whether adjudication determination made out of time invalid
ACTS CITED: Building and Construction Industry Security of Payment Act 1999 - The Housing Grants, Construction and Regeneration Act 1996