- Home
- Nomination
- UK Cases
- Overseas Cases
- Panel
- Guidance
- Glossary
- Legislation
- England & Wales
- Wales
- Scotland
- Northern Ireland
- Australia (Australian Capital Territory)
- Australia (New South Wales)
- Australia (Northern Territory)
- Australia (Queensland)
- Australia (Southern Territory)
- Australia (Tasmania)
- Australia (Victoria)
- Australia (Western Australia)
- Eire
- Isle of Man
- Malaysia
- New Zealand
- Singapore
- Links
- Contact Us
Case Study Archive
Below you can see our full case archive.
There are a total of 1503 cases in our archive-
13th June 2001Mitsui Babcock Energy Services Ltd [2001] ScotsCS 150This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes In determining "construction operations" under s105(2)(c) HGCR Act 1996, the adjudicator should look at whether the object of the "construction operation" was to further the activities described in s105(2)(c). Lord Hardie, Outer House, Court of Session 13 June 2001 In September 1999, M and the first respondent (FWE) entered into a contract. FWE was required to deliver prefabricated equipment and piping to the site; M was to assemble the equipment into two complete boiler plants on land within a petrochemical complex operated by a BP company at Grangemouth. The boilers were constructed on behalf of and operated by CHP who was contracted to sell the steam to BP. In July 2000, M issued a Notice of Adjudication concerning FWE's alleged failure to pay...
-
1st June 2001Faithful & Gould Ltd v Arcal Ltd [2001] Case No: E190023 TCCThis summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes An adjudicator must be a natural person acting in his personal capacity, however, there is no rule which says he must sue for his fees in his own name. Technology and Construction Court (Newcastle Upon Tyne District Registry) 25 May 2001 Two applications were heard: the first related to the Defendants' contention that the Claimant's claim should be struck out as disclosing no cause of action. Their case was that the adjudicator, G, sued for his fees under the name of the company where he was employed rather than in his personal capacity and the role of an adjudicator must be carried out by an individual. The judge rejected this, seeing no reason why G, who happened to work in a company that administered his fees, should have to sue for his fees...
-
31st May 2001Fence Gate Ltd v James R Knowles Ltd TCC 25/01 SF102200 [2001]This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes Disputes relating to payment for appearing as a witness of fact and for assisting at an arbitration are not disputes "in relation to construction contracts" in accordance with s105 of the Act and therefore an adjudicator does not have jurisdiction to act in relation to these. HHJ Gilliland, Technology and Construction Court 31 May 2001 F appointed J under a contract to provide architectural and surveying services described as "Preliminary Report on defective kitchen floor" and also to provide evidence as a witness of fact as an architect or engineer and assisting in an arbitration as an architect or engineer. J claimed payment under 4 invoices in respect of services rendered to F under the contract. The matter was referred to adjudication; the...
-
22nd May 2001A De Gruchy Holdings Ltd v House Of Fraser (Stores) Ltd [2001] TCC. HT 00 -186
-
15th May 2001Re A Company (number 1299 of 2001) [2001]This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-lawnow.com/adjudication In the absence of an s111 withholding notice, it is not possible to advance an abatement or set-off against the sum demanded (even if defective work was not apparent at the time a notice should have been given). A winding-up petition based on a statutory demand for a sum due may be restrained where the cross-claim is genuine and serious, exceeds the sum due and is one which the company has been unable to litigate. Deputy HHJ David Donaldson, Chancery Division CCL was the main contractor in the construction of 4 houses and engaged a roofing sub-contractor, GAL. CCL terminated GAL's contract after about 2 months and left outstanding the sum of £9,702.47 on 2 valuations. GAL served a Statutory Demand on the alleged debt. CCL sought a final injunction to prevent GAL...
-
9th May 2001RJT Consulting Engineers Ltd v DM Engineering Ltd [2002] BLR 217HHJ MacKay considered an application for a declaration that the agreement between the parties was not an agreement in writing as provided for by section 107 of the HGCRA. HHJ MacKay said that section 107 was an inclusive not an exclusive piece of legislation. The purpose of the act was to bring in agreements which would not be caught otherwise by the act to enable parties to construction agreements to take advantage of the procedure set out in the act. The material between the parties by way of written subsidence (i.e. such as to evidence the agreement in writing) was "comparatively great". If it were necessary to insist upon a recitation of the agreement when the existence of the agreement, the parties to the agreement, the nature of the work and a price of that agreement are clearly to be found in documentary form then this would be contrary to the terms of the HGCRA.
-
20th April 2001Farebrother B.S. Ltd v Frogmore Investments Ltd [2001] SF101587This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes Under the TeCSA Adjudication Rules 1999, the adjudicator can rule on his own jurisdiction and the scope of the adjudication. Such decision would be binding on the parties. The approach in KNS Industrial Services v Sindall was approved. HHJ Gilliland QC, Technology & Construction Court 20 April 2001 FI employed FBS as a building contractor. A dispute arose over the extension of time due to FBS, and FBS submitted this dispute to adjudication under the TeCSA Adjudication Rules (1999). FBS's notice of adjudication sought an extension of 22 weeks together with additional payment for loss and expense. FBS' subsequent referral notice sought a longer period of time. FI alleged that FBS was in critical delay and sought to set off other sums by way of...
-
11th April 2001Austin Hall v Buckland Securities Ltd [2001] HT 00 477This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes Adjudication is not subject to the Human Rights Act 1998. An adjudicator is not a public authority since he is not a tribunal deciding legal proceedings. Further, the Court should also take into account the Court enforcement proceedings when considering if there has been a breach of a Convention right HHJ Bowsher QC, Technology & Construction Court 11 April 2001 B employed A to carry out building works on the terms of the JCT Agreement for Minor Building Works. B did not pay A's final account so A referred the dispute to adjudication. The adjudicator found in A's favour. A applied for summary judgment to enforce the adjudicator's decision. This was the first "frontal assault" on adjudication under the Human Rights Act 1998 ("HRA"). B resisted...
-
11th April 2001Discain Project Services Ltd v Opecprime Developments Ltd No2 [2001] EWHC TCC 435This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes HHJ Bowsher QC, Technology & Construction Court Where there has been a substantial and relevant breach of the rules of natural justice, and where an objective bystander could conclude that the adjudicator was or may be biased, the Court would refuse to enforce his decision. 11 April 2001 This is the Court's judgment following a full trial of the dispute concerning the enforceability of the adjudicator's decision, after the Court refused summary judgment (see page 46 above). The Court invited the adjudicator to be joined to the action. The adjudicator did not so wish, but he was called by the Court as a witness so that he could be cross-examined by both parties, and he also filed written submissions. The complaint about the adjudicator's conduct...
-
13th March 2001Watson Builders Service [2001] ScotCS 60This summary was provided by CMS Cameron McKenna LLP. For more information visit http://www.cms-cmck.com/Construction/Construction-Disputes An Adjudicator has the power to determine the meaning of the sub-contract terms even if this results in him determining a dispute about the validity of his appointment and therefore his jurisdiction. Lady Paton, Outer House Court of Session (Scotland) 13 March 2001 W were appointed as main contractors to carry out building works at a church in Glasgow. They entered into a sub-contract with the second respondents, Miller (Preservation) Ltd, in respect of rot eradication. The sub-contract documents comprised a quotation dated 2 February 1999 and counter-offer dated 24 April 1999. The parties agreed that the sub-contract was a "construction contract" within the meaning of s104 of the HGCRA. A dispute arose in relation to the sub-contract work. Miller...