Standard Form of Agreement between a Householder and Building
Contractor
Between
(the
Householder)
and
(the
Building Contractor)
- The Building Contractor will carry out and complete the work described in
the Schedule of Works at Appendix 1 (called the Works), for which the
Householder shall pay the Building Contractor the contract sum of £
..including,
where chargeable, VAT. Subject only to any adjustment permitted and made
under this Agreement.
- The Works may be started between
.. and
., and shall be
completed to a standard of completion suitable for immediate occupation and
use, as intended, by
- Payment will be made in accordance with the schedule at Appendix 2.
- The Householder shall, by written notice, extend the date for the
completion in relation to matters outside the control of the Building
Contractor, but it is agreed that inability to obtain suitable tradesmen
shall not be regarded as outside the control of the Building Contractor.
- The Building Contractor will make good, at his own cost, any defects in
materials or workmanship of which the Householder notifies to the Building
Contractor in writing within a period of three months after satisfactory
completion referred to in 2 above.
- The Householder may order the Building Contractor, only in writing, to
make a change in the content of the Works, or to delay some part. If the
change will increase the Contract Sum, no additional payment shall be due
unless the Building Contractor agrees the revised contract sum before making
the change. (the agreement to increase the contract sum is a condition
precedent to the Building Contractor being paid for the change). If the
change should reasonably reduce the Contract Sum, then a fair and reasonable
amount shall be deducted from the Contract Sum.
- The Building Contractor may initiate a change and may request additional
or reduced payment. No change to the Contract sum shall be made unless the
Householder has so agreed, prior to the change being implemented.
- If the Works are not complete by the date fixed under this Agreement the
Building Contractor will pay or allow the Householder, either under this
Agreement or as a debt, liquidated damages at the rate of £
.per
day from the date fixed for completion until actual completion.
- Unless otherwise agreed in writing with the Householder, the Building
Contractor will comply with the requirements of any statute, statutory
instrument, rule, order, Building Regulation or bylaw applicable to the
Works and shall pay all related fees and charges due from him.
- Unless otherwise agreed in writing with the Householder, the Contractor
shall indemnify the Householder against and shall take out and maintain
adequate insurance against all losses resulting from:
- personal injury or death directly related to the carrying out of the
Works by the Building Contractor; and
- damage to the Works and/or other property directly related to the
carrying out of the Works by the Building Contractor.
-
failure of the Building Contractor, his consultants or
sub contractors, to properly design any works, the design of which, have
been entrusted to him.
-
If the Building Contractor fails, on request, to provide
satisfactory documentary evidence of such insurance the Building
Contractor's entitlement to payment under this Agreement shall be postponed
until such satisfactory documentary evidence is provided.
- If either party fails, without reasonable cause, to comply with the terms
of this Agreement, then the other party may give written notice requiring
the default to be ended. If the default continues for 7 days after receipt
of the notice then the employment of the Building Contractor may be
terminated upon receipt by the defaulting party of a further written
notice stating that the employment of the Building Contractor is terminated
forthwith. The Building Contractor will then be entitled to payment for work
carried out that is reasonable in all the circumstances of the
determination, provided that the Householder may deduct reasonable expenses
incurred in obtaining a new Contractor if the Building Contractor was the
only defaulting party.
- Any dispute or difference under this Agreement may be referred by either
party to adjudication by a person nominated by adjudication.co.uk in
accordance with and subject to their Rules for Adjudication current at the
time of referral. The Adjudicator's decision will be given within 28 days of
referral, unless extended to 42 days by the referring party, and will be
binding on the parties until the dispute or difference is finally determined
by legal proceedings or by agreement.
Signed by the Householder
..
Date:
..
Signed by or on behalf of
The Building Contractor
.
Date:
.
Appendix 1 Schedule of Works
- Drawings approved under The Town & Country Planning Acts and Building
Regulations
..
- Other drawings as listed
..
- Scope of Works/specification
..
- Aspects of work excluded from the Schedule of Works *:
- Digging for, and laying, foundations to a depth greater than shown
on the drawings or described in the Schedule of Works
.
- Drains and manholes, other than shown on drawings
- Special glazing
.
- Decorations
..
- Kitchen fittings
- Plumbing
.
- Central heating
.
- Bathroom fittings
- Light fittings
.
- Gardening or landscaping
(* this is a list of work which will not be carried out by
the builder, therefore cross out works which you want included and add any other
items excluded)
Appendix 2 Payment schedule
|
Description of work to be completed prior to a part
payment
|
Percentage of contract sum
|
or
|
Agreed lump sum
|
Date paid
|
| |
|
Mobilisation fee
|
|
|
|
|
|
Foundations, ground floor slab, dpc and damp proof
membrane
|
|
|
|
|
External walls and first floor level
|
|
|
|
|
Roof and windows, including glazing
|
|
|
|
|
All internal electrical and plumbing services
|
|
|
|
|
Fittings/completion
|
|
|
|
|
Retention **
|
|
|
|
** Retention shall be paid within 1 week of satisfactory
remedial works, after 3 months from the completion of the works.