Case Number: HT-99-289
IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
HIS HONOUR JUDGE HUMPHREY LLOYD QC
B E T W E E N:
|
F W COOK LIMITED |
Claimant |
|
|
and |
||
|
SHIMIZU (UK) LIMITED |
Defendant |
Case Number: HT-99-289
Date of Judgment: 4 February 2000
This was an application under Part 24 of the CPR to enforce an adjudicator's decision given pursuant to the TecSA Rules, version 1.2. The defendant had paid what it considered was due. The questions turned on the meaning to be given to the notice of adjudication or letter of referral and to the decision itself (and on whether the decision might have been outside the jurisdiction of the adjudicator). For the reasons that appear from the judgment the application was dismissed.
Michael Bowsher appeared on behalf of the claimant, instructed by Shadbolt
& Co,
David Thomas appeared on behalf of the defendant, instructed by Edge Ellison.
JUDGMENT
"The writer visited Mr Stannard [to whom the letter was being sent] at your offices on 22 September 1999. We observed that our provisional final account figure was circa £2.4 million compared with your valuation of circa £1.8 million, and that such significant differences of opinion existed between our respective colleagues as to the value of variations, acceleration, delay, disruption and contra charges that it was unlikely that we could agree the final account without involving third parties.
"We emphasised that we preferred to negotiate with yourselves in a professional way, but that unless you felt able to make movements towards us on certain key issues we would use adjudication. To date we have had no meaningful response from yourselves.
"Accordingly, please accept this letter as notice of our intent to refer the following disputes to adjudication under the ORSA Adjudication Rules:
"1. Reinstatement of the agreed sum for acceleration circa £72K.
"2. Removal of negative variations for work not within the scope of our subcontract circa £60K.
"3. Removal of contra charges not relevant to our activities circa £80K.
"4. Release of half retention monies circa £45K.
"We will present detailed figures to the adjudicator and they may differ from the above."
"I find and hold that the respondent was entitled to deduct £29,146.24 plus VAT but has wrongfully deducted a further £61,000.90 plus VAT, and the referring party is entitled to recover the said sum of £61,000.90 plus VAT from the respondent."
"I find and hold that the respondent is entitled to items of set-off amounting to £67,068.70 plus VAT, but has wrongfully deducted a further £55,035.65 plus VAT, and the referring party is entitled to recover the same from the respondent."
"I direct that all sums payable pursuant to this decision shall be paid by the respondent to the referring party within seven days of the date hereof, save that my fee shall be paid to me within seven days of the date of the invoice."