SILVERPOINT INTERNATIONAL LIMITED AND ORS V WEDDING EARTHMOVERS LIMITED HC AK CIV 2007-404-104 [2007] NZHC 807 (17 August 2007)
IN THE HIGH COURT OF NEW ZEALAND
AUCKLAND REGISTRY
CIV 2007-404-104
UNDER The Companies Act 1993
IN THE MATTER OF an application under Section 290 to set
aside a statutory demand
BETWEEN SILVERPOINT INTERNATIONAL LIMITED
AND CIV 2007-404-105
MCLAUGHLIN PARK LIMITED
AND CIV 2007-404-106
FAVONA DEVELOPMENTS LIMITED
AND CIV-2007-404-107
PACIFIC BRIDGE LIMITED
Applicants
AND WEDDING EARTHMOVERS LIMITED
Respondent
Hearing: 14 August 2007
Appearances: A Barker for Applicants
C Andrews for Respondent
Judgment: 17 August 2007 at 12 noon
JUDGMENT OF ASSOCIATE JUDGE DOOGUE
[on costs]
This judgment was delivered by me on 17.08.07 at 12 NOON, pursuant to
Rule 540(4) of the High Court Rules.
Registrar/Deputy Registrar
Date...............
Counsel
A Barker, - by email -
barker@xtra.co.nz
McVeigh Fleming, P O Box 4099, Auckland
SILVERPOINT INTERNATIONAL LIMITED AND ORS V WEDDING EARTHMOVERS LIMITED
HC AK
CIV 2007-404-104 17 August 2007
[1] I gave my judgment in this proceeding on 30 May 2007. In paragraph 149 of that judgment I said that I would make orders as to costs with if the parties were unable to resolve that issue by agreement. The parties were not able to agree and I heard argument on 14 August 2007.
[2] The first relevant matter is that costs are at the discretion of the Court. In exercising that discretion there are certain principles which set out in Rule 47 that provide guidance. The first concerns the matter of which party should pay costs. R47(a) says that the party who fails with respect to a proceeding or an interlocutory application should pay costs to the party who succeeds. That principle has relevance in this case. However the parties did not seem to be able to agree on the extent to which the applicant had been successful and the respondent unsuccessful. There was argument about whether the judgment that I gave should be regarded as one proceeding or whether it was a composite judgment affecting four
different proceedings.
[3] The correct approach is to look at the matter on a proceeding by proceeding basis. The rules mandate such an approach. Rule 46 speaks of:
Costs of and incidental to a proceeding or a step in a proceeding.
[4] Rule 47(a), which I have already mentioned, refers to "a proceeding or an
interlocutory application". The fact that matters are heard together would not seem
to be any ground for approaching the fixing of costs on other than a proceeding by
proceeding basis. The fact that common affidavits were provided and that a
composite judgment was given may be a factor which is to be taken into account as
part of the Courts overall discretion in fixing costs, though.
[5] Approaching the matter on a proceeding by proceeding basis, the question I
pose is which party was successful on each of the applications before me. The
applications were applications to set aside statutory demands.
[6] I granted the application of Favona Developments, Pacific Bridge Limited
and Silverpoint International Limited. I dismissed the application of McLaughlin
Park Limited ("MPL"). I dismissed MPL's application because there was no
reasonably arguably basis upon which MPL could dispute part of the claim by
Wedding Earthmovers Limited ("WEL") - the approximate amount owing being
$222,000. Nor would I accept the argument for MPL that it was entitled to set off
against that debt another debt that it claimed WEL owed to a related company, Favona.
[7] The starting point is that the applicants, with the exception of MPL, should
have costs. I accept Mr Barker's submission that the fact that I commented that at
least one of the applications succeeded only by a narrow margin, does not justify
the conclusion that the applicant should not have costs.
[8] The respondent should have costs on the MPL proceeding.
[9] The next matter concerns the correct categorisation of the costs award. The
parties accept, and correctly in my view, that the proceeding is a category 2
proceeding. They also accept, again correctly, that Band B should apply.
[10] The next issue concerns the time allocation for phases 30 and 31 in schedule
three to the Rules. Those two phases concern the time that should be allocated for
preparing for hearing and appearance at the hearing.
[11] The hearing took 1.75 days. Obviously, at various stages of the proceeding,
attention was focused on one or other of the applications. It was not the case that
1.75 days was spent on all of the applications. The parties were not able to agree as
to how much time was spent on each application.
[12] I do not consider that minute calculations can helpfully be attempted. I am of
the view that the matter should be viewed in the round and that the proper approach
is to break the time down as follows:
a) Favona Developments Limited ("FDL") 1 day
b) MPL 0.5 day
c) Silverpoint International Limited and Pacific Bridge Ltd
between them 0.25 day
[13] Because time is measured for the purposes of Schedule 3 in ¼ day lots, it will
be possible for the parties to calculate the costs entitlements on the basis of the
determination I have just set out.
[14] It is not feasible to further split the ¼ day time allocation between Silverpoint
and Pacific Bridge. I do not intend to attempt that exercise. The parties can either
approach matters on the basis that an order for costs for the ¼ day appearance and
preparation should be allocated to one proceeding or the other. Or, if they cannot
agree, I will split the sum arrived at by a 2B calculation equally between the two
proceedings. I hope that this indication is sufficient to enable the parties to resolve
that issue without further recourse to the Court.
[15] In each case, the determination of the appropriate hearing time also resolves
the question of proper allowances for preparation time.
[16] The effect of the time allocations that I allow will be that for preparation and
hearing costs, the applicant will have costs calculated on a 2B basis for 1 ¼ days and
the respondent costs on the same basis for one ½ day. In addition disbursements are
allowed to each side as fixed by the Registrar.
[17] If there are any matters I have overlooked, counsel should ask the Registrar
to list the matter in my next Chambers List.
J.P. Doogue
Associate Judge