IN THE DISTRICT COURT AT NORTH SHORE

 

BETWEEN T U F PANEL CONSTRUCTION LIMITED

Plaintiff

 

AND ROBERT ERNEST CAPON

Defendant

 

 

Hearing: 25 February 2004

 

Appearances: Mr Scof Galloway for Plaintiff

Mr Brian Stewart & Ms Everitt for Defendant

 

Judgment: 15 March 2004

 

RESERVED JUDGMENT OF JUDGE D M WILSON QC

 

- - ---

 

INTRODUCTION

 

[I] This application for Summary Judgment is brought under the Construction

Contracts Act 2002. It arises out of contracts for the supply of concrete panels by

the plaintiff for construction work being undertaken on property in Albany, North

Shore City by the defendant.

 

 

[2] The Construction Contracts Act 2002 received the Royal assent on 26

November 2002 and applies to construction contracts entered into after 1 April 2003.

Counsel advise that this case is one of the first cases, if not the first case, to reach the

courts under the Act . The case calls for an examination of the impact on construction

contracts of a radically changed legal matrix.

 

 

FACTUAL BACKGROUND

 

[3] Mr J A Brennan, of the plaintiff company, after speaking to the defendant

prepared a tender document on the letter head of the plaintiff company, addressed to

'Mr Robert Capon, 4 Dallan Place, Albany' dated 3 June 2003 for construction of

concrete panels at that address. The defendant accepted this tender. He signed it ' R

Capon' against the words 'Confirmation of agreement and approval to go ahead and

proceed, signed for and on behalf of Robert Capon' and returned it to the Plaintiff

Company.

 

 

[4] The Plaintiff Company commenced the construction of the concrete panels

accordingly.

 

 

[5] The plaintiff prepared and sent a second tender document in the same form

dated 6'" August 2003 to 'Mr Robert Capon' at 6 Dallan Place, Albany. It mistakenly

referred construction of concrete panels for number 4 Dallan Place but was in fact,

as everyone understood, for concrete panels at number 6 Dallan Place, the address to

which the tender had been sent. Mr Capon advised his acceptance of this tender by

telephone.

 

 

[6] Two progress payments were made to the Plaintiff ,Company:

 

A cheque for $8,000 drawn on the account of Newco Construction Limited deposited on or about 24th July 2003.

 

A cheque for $1 1,000 drawn on the account of Crearnala Developments Limited deposited on or about 20th August 2003.

 

 

[7] Invoices for the progress payments (not particularly notable for care in their

preparation) were prepared on the plaintiffs letterhead and sent to 'Mr Robert

Capon, Newco Construction Limited, PO Box 300335, Albany 'for the attention of

Mr Capon', The second o f the invoices gave credit for both of the payments made to

the Plaintiff Company.

 

 

[8] Mr Brennan deposed that he knew of that address because he had, some time

after the contract started, been given a business card in the name of Newco

Construction Limited showing Mr Capon's name and giving the address above.

 

 

[9] The plaintiff company served formal Payment Claims on the defendant

personally on 15th September 2003 addressed to 'Mr Robert Capon', respectively at

number 4 Dallan Place Albany and at number 6 Dallan Place, Albany.

 

 

[l0] The only written response was a letter dated 16 September 2003 addressed to

the plaintiff company on the letter head of Crearnala Developments (2003) Limited

and signed 'Robert Capon', The address and contact details on the letterhead were

the same as on the Newco Construction Limited business card, which Mr Capon had

given Mr Brennan. The letter raised concerns about the contractual arrangements

and sought 'accounts as you agreed on a cost plus basis for both sides'. It raised no

suggestion that Mr. Capon was not the contracting party.

 

 

[11] The Payment Claims have not been settled and the present proceedings for

summary judgment were issued on 6 November 2003.

 

 

LEGISLATIVIE BACKGROUND

 

[12] Both contracts came into being after the commencement of the Construction

Contracts Act 2002 which, as the parties accept, applies to the contracts in issue in

these proceedings: Section 9 applies to every construction contract whether or not

governed by New Zealand law but related to carrying out construction work in flew

Zealand and was entered into on or after the date of commencement of the Act and is

written or oral or partly written and oral.

 

 

[13] Under the previous law the factual background was often disconcertingly

complex and the courts were understandably reluctant to deal with such cases by

way of summary judgment, leaving contractors with the prospect of having to carry

litigation through to a full hearing, abandon their claim, or settle for substantially

less than their full entitlement.

 

 

[14] A general policy statement is set out at the beginning of the explanatory note,

which accompanied the bill when it was first introduced to the House of

Representatives on 15 May 2001.

 

This bill is intended to facilitate prompt and regular payments within the

construction industry. Typically, construction industry contracts provide for

work to be paid after the work has been carried out. Payments are usually

made by instalments, as the work progresses, but they are very seldom made

in advance. This pattern of payments often means that a developer, principal, or head contractor with cash flow problems may deliberately delay

payment for work done and, in effect, use those further down the contractual

chain (for example sub contractors) to partly finance the construction

project. It aIso means that, if a developer or principal becomes insolvent,

head contractors and sub contractors may not be paid at all for the work that

they have already carried out.

 

 

[15] The purpose of the Act is set out in section 3, which provides as follows:

3 Purpose: The purpose of his to reform the law relating to

construction contracts and in particular -

 

(a) to facilitate regular and timely payments between the

parties to a construction contract; and

 

(b) to provide for the speedy resolution of disputes arising

under a construction contract; and

 

(c) to provide remedies fir the recovery of payments

under a construction contract,

 

 

[16] In the text 'Progress Payments and Adjudication' by Smellie J CNZN QC the

retired High Court Judge comments on the payment claim system. I adopt the tenor

of his analysis with respect:

 

The Construction Contracts Act 2002 is as much about prompt payment of

progress claims as it is about a rapid form of interim resolution

(adjudication) when the payments claimed are in dispute. The essence of

those provisions is that there must be a more or less immediate response to a

claim (20 working days) in default of which the amount is recoverable as a

debt due ,together with actual costs of getting judgment. So progress

payments can no longer be ignored, and the time and cost of enforcing

payments through the courts should in future fall less heavily on the unpaid

contractor or sub contractor. In addition, there is the right to suspend work.

 

 

[17] The mechanisms provided by the Act for dealing with payments are a

'payment claim' under section 13 and a 'payment schedule' under section 15. Both

must meet formal requirements.

 

 

[18] A payment claim is served by the payee on the payer and must (under section 20(20));

 

  1. be in writing; and

  2. contain sufficient details to identify the construction contract

to which the progress payment relates; and

  1. identify the construction work and the relevant period to which the progress payment relates; and

  2. indicate a claimed amount and the due date for payment; and

  3. indicate the manner in which the payee calculated the claimed amount; and

  4. state that it is made under the Construction Contracts Act.

 

 

[19] When a payer receives a payment claim, he or she can respond by providing

the payee with a 'payment schedule.' This is his or her opportunity to agree or

disagree with the amount claimed.

 

 

[20] The payment schedule provided to the payee must:

 

(a) be in writing; and

 

(b) identify the payment claim to which it relates; and

 

(c) indicate a scheduled amount (section 2 l(2)).

 

 

[21] A "scheduled amount' means an amount of progress payment specified that

the payer proposes to pay to the payee in response to a payment claim: (section 19).

 

 

[22] Section 21 (3) requires inclusion of

 

(a) the manner in which the payer calculated the scheduled amount; and

 

(b) the payer's reason or reasons for the difference between the scheduled amount and the claimed amount; and

 

(c) in a case where the difference is because the payer is

withholding payment on any basis, the payer's reason or

reasons for withholding payment.

 

 

[23] Where no payment schedule is provided, and no payment is made on the payment claim, the payee:

 

(a) may recover from the payer, as a debt due to the payee, in any court -

 

(i) the unpaid portion of the claim amount; and

 

(ii) the actual and reasonable costs of recovery awarded

against the payer by that court. (section 23 (2)).

 

 

THE CONTRACTS IN ISSUE: Foundation of dispute

 

[24] The contractual arrangements in this case were in a partly oral and partly written form. Work was carried out in accordance with those contracts by the plaintiff company between June 2003 and 9 September 2003. Common terms were that -

 

(b) Progress claims were to be paid within 14 days from the date of

claim.

 

(c) The contract would be subject to nil retentions on monies for

work completed.

 

 

[25] The contract price for 4 Dallan Place was $7l,355 based on 1168 square

metres, with any additional work to be charged out at the rate of $59.46 per square

metre. An oral variation concerned the terms under which a labourer would be

employed.

 

 

[26] The contract price for 6 DaIlan Place was $39,600 based on 620 square metres, with any additional work to be charged out at the rate of $63.87 per square metre-

 

 

ANALYSIS

 

[27] The two separate payment claims under the Construction Contracts Act 2002

were served on the defendant personally on 15 September 2003. The sole reply from

Mr Capon on the letter head of Creamala Developments (2003) Limited, did not

mention a 'schedule account’. It did not identify the payment claim to which it

related and did not indicate a 'scheduled amount', It did not attempt to meet the

requirements of Section 21(3) .It did not purport to be a 'payment schedule' under

the Construction Contracts Act and it was not. Mr. Stewart did not attempt to argue

that it was. No payment schedule has ever been provided.

 

 

[28] In the absence of a payment schedule within the time provided section 22

applied to make the defendant liable to pay the amounts claimed in the payment

claims. Section 22 provides as follows:

 

22. Liability for paying amount claimed

 

A payer becomes liable to pay the claimed amount on the due date for

the progress payment to which the payment claim relates if –

 

(a) a payee serves a payment claim on a payer; and

 

(b) that the payer does not provide a payment schedule to the

payee within

 

(i) t he time required by the relevant construction contract; or

 

(ii) if the contractor does not provide for the matter, 20 working days after the payment claim is served.

 

 

[29] The legal consequences of not paying the claimed amount where there is no

payment schedule are that the payer becomes liable to pay the unpaid portion of the

claimed amount to the payee under section 23 as a debt due (section 23(2)) together

with the actual and reasonable costs of recovery (Subsection (2)(a)(ii)).

 

 

[30] In my judgment the Act was specifically designed to relegate to history losses

within the construction industry being borne by those further down the contractual

chain who are in the worst position to bear them because there was no effective way

to enforce progress claims during the contract,

 

 

[31] In my view the policy of the Act and the provision to which I have referred

establish that for construction contracts to which h e Act applies, the claims for

progress payments crystallise once a payment claim has been issued in respect of the

work to which the payment claim relates, provided only that it meets the

requirements of form under s20 of the Act and assuming, as here, that no payment

schedule is forthcoming.

 

 

DEFENCES

 

[32] The defendant raised the following matters in his Notice of Opposition, namely:

 

[32.1] The plaintiff has issued proceedings against the wrong defendant

 

[32.2] The correct defendant has a set-off or counter claim that equals or exceeds the amount of the plaintiffs claim;

 

[32.3] The plaintiff did not complete the contract works;

 

[32.4] The payment claims issued by the plaintiff do not comply with the Construction Contracts Act 2002;

 

[32.5] Summary judgment is inappropriate in the context of a building dispute;

 

[32.6] As appeared in the affidavit of Robert Ernest Capon

 

I deal with those submissions now.

 

[32.1] The plaintiff has issued proceedings against the wrong defendants

 

[32.1.1] Mr Stewart for the defendant submitted that there was a genuine

conflict of evidence over who were the parties to the construction contracts and that

it was inappropriate for the Court in a summary judgment context to assess the

credibility of the parties' statements in their affidavits.

 

[32.1.2] The Court is not bound to 'accept uncritically as raising the dispute of

fact which calls for further investigation on an affidavit however unequivocal,

lacking in precision, inconsistent with undisputed contemporary documents, or other

statements made by the same deponent, or inherently improbable in itself it may be'.

The Court is entitled to act on a more robust and common-sense manner and in

summary judgment cases in New Zealand it is not obliged 'meekly to accept without

question whatever unvarnished statements may happen to be made on affidavit':

United Homes (1988) v Workmen [2001] 3 NZLR 447,452 per McGechan J, Cout

of Appeal.

 

[32.1.3] The present assertion by Mr Capon that the true contracting party was

one of his companies fails to meet the test of comparison with contemporaneous

documents. The most significant of these is the original tender document of 3 June

2003 which Mr Capon took away with him over night and returned the next day. It

had been addressed to him at the place where the work was to be done and he had

signed his name against the words 'Confirmation of agreement and approval to go

ahead and proceed - signed for and on behalf of Robert Capon'.

 

[32.1.4] Although the same words appeared at the end of the next tender

document dated 6 August there is no evidence that Mr. Capon hedged his discussion

in any way when he rang to confirm his acceptance of that tender.

 

[32.1.5] The fact that subsequently invoices were addressed. to Mr Robert Capon at the Newco Construction Limited address is, in my view, insignificant. That was simply an address. It does not detract from the clear position that Mr Capon was the contracting party.

 

[32.1.6] Furthermore the two payment claims were addressed to 'Mr Robert Capon' at the two addresses in Dallan Place, Albany where the work had been done.

 

[32.1.7] The response to that was a letter signed by Mr Capon on 16 September 2003 on the letterhead of Crearnala Developments (2003) Limited. He did not then challenge the fact that he was personally named as the payer in the payment claims. Mr Capon in his affidavit neither explains whether he noticed the payment claims were addressed to him personally or whether he failed to raise the issue because of an oversight.

 

[32.1.8] The Court of Appeal considered a similar situation in Orrell v Midas

Interior Design Group Limited (1991) 4 PXNZ 608. That was a summary judgment

application against a number of defendants, including individuals trading as a joint

venture. The individuals opposed summary judgment on the ground that the debt

was owed by a limited liability company. The affidavits in that case were described

as 'the model of vagueness by the Court: of Appeal at page 612. Bald assertions that

the plaintiff 'knew he was dealing with the company' made without reference to the

substance of the conversation in which this was alleged to be made known, failed to

indicate any substance in the defence. Their bare assertions as to the plaintiff's

knowledge did not pass the threshold of credibility (op cit page 613).

 

[32.1.9] In the present case, Mr Capon's evidence on the crucial point is in

these words: 'Mr Brennan was clearly told he was working for Newco' and the

second 'at our first meeting Mr Brennan was given Newco's name as the contracting

party'. No detail is given about where the conversation took place, or the context of

the conversation.

 

[32.1.10] Having regard to the vagueness of the assertion, the responsibility of

Mr Capon to convey plainly that the contract was with the company and not him

personally under the doctrine of undisclosed principal, the contemporaneous

documents, the signature by Mr Capon on his own behalf on the initial tender

document, the assertions of Mr Capon that his company was the contracting party,

and that he told Mr. Brennan of that, fail to pass the threshold of credibility.

 

[32.2] The correct defendant has a set-off or counter-claim that equals or

exceeds the plaintiffs claim.

 

This was an attempt to set up matters alleged to be available to Newco Construction Limited.

 

In view of the factual finding that the present defendant is the correct defendant, and that the specific provisions of section 79 of the Act exclude counterclaims, set-offs, or cross-demands except in circumstances which do not apply here, this defence must fail.

 

 

[32.3] The plaintiff did not complete the contract works

 

Mr Stewart did not pursue this defence.

 

[32.4] The payment claims issued by the plaintiff do not comply with the

Construction Contracts Act 2002

 

[32.4.1] Mr Stewart submitted that from a policy standpoint, shoddy claims

should not be upheld.

 

[32.4.2] He said that serious consequences could flow from a failure to follow

the tight formal and time requirements under the Act.

 

[32.4.3] They might lead to the injustice of a disorganised defendant having to

make early payment of an unjustified claim. He submitted that the plaintiff should

'get it right' and that this plaintiff did not. Despite a valiant effort he was unable to

establish in argument any way in which the payment claims fell short of the formal

requirements of section 22.

 

[32.4.4] Even assuming that Mr. Stewart is right in his submissions on tlic policy underlying the Act, I find that his argument fails on the facts:

 

The payment claims were in writing : section 20(2)(a);

 

They identified the construction contracts to which the progress payments related (section 20(2)(b);

 

They identified the construction work as being manufacture of tilt panels

 

They showed the relevant period (section 20(2)(c));

 

They showed the chimed amount and the due date for payment (section 20(2)(d ));

 

They indicated the manner in which the payee calculated the claim by reference

to the number of metres by the square metre rate and the percentage of work

done (section 20 (2)(e));

 

Due credit was given for variations to the contract in relation to wages and a

deduction of the two previous payments totalling E 19,000 was allowed for

because the deduction of $16,888.90 shown was the GST exclusive element of

the payments.

 

The payment claim forms used by the plaintiff is the one approved by the New

Zealand Sub-Contractors Federation Incorporated.

 

They specifically stated that they were made under the Construction Contracts

Act 2002 (section 20(2)(f).

 

[32.4.5] In my view, and contrary to the thrust of Mr. Stewart's submissions

on policy, the Act makes it clear that parties must be pro-active in resolving those

matters while they are still fresh. This does not mean that a defendant permanently

loses the opportunity of having his issues dealt with. The Act provides in Part 3 for

a fast track adjudication procedure for disputes under construction contracts, But that

procedure does not stand in the way of summary judgment being obtained by the

payee, nor does it stand in the way of enforcing payment once judgment has been

obtained.

 

[32.4.6] I am satisfied that the formal requirements of s20 are fulfilled. In

Australia where similar legislation has been in force for some time it has been held

that technical quibbles that formal requirements had not been complied with will

receive scant attention: Hawkins Constructions (Australusia) Ply Ltd v Mac's

Industrial Pipework Pty Ltd [2001] NSWSC 815 per Windeyer J. A similar

approach may be apt in New Zealand, The issue does not arise in this case and I

express no concluded view on it.

 

[32.5] Summary Judgment is inappropriate in the context of a building

Dispute.

 

[32.5.1] The scheme of the Act acknowledges that differences arise between

parties over payment claims and it sets up a mandatory system for those to be

crystallised at the time by the filing of a payment schedule.

 

[32.5.2] When a payment schedule is not forthcoming from the contractor/payer, the payee may proceed under the statute to claim the amount as a debt due under section 23 (2)(a). Previous authority to the effect that summary judgment proceedings are inappropriate in the context of a construction dispute has been overtaken and can now be firmly put aside.

 

[32.6] The final matter raised by way of defence was a reference to matters

that ' appear in the affidavit of Mr Capon'.

 

[32.6.1] In my view this type of pleading in a Notice of Opposition is too

vague and is unsatisfactory. However here the plaintiffs counsel did not claim to

have been caught by surprise, I now deal with the matter raised in argument under

this head.

 

[32.6.2] The defendant asserted in his affidavit &at a binding variation to the

contracts was entered into orally on Monday, 8 September 2003 when he says that

Mr Brennan agreed to his paying cost plus 10% on both sites. Mr. Brennan deposed

that he never agreed to accept less than the full amount owing to the plaintiff but

provided an amended invoice to correct an earlier error and a list of costs and

expenses in an attempt to get some money.

 

[32.6.3] I accept the submission for the plaintiff that there is no advantage to a

plaintiff in agreeing to waive its contractual rights to payment and that to do so

would be, in the words of Master Venning (as he then was) "commercial1y

unrealistic and inherently improbable" There was an understandable advantage in

providing the information sought to improve cash flow from the defendant who was

pressed for funds.

 

[32.6.4] There is no room to regard the faint and vague suggestion of accord

and satisfaction as passing a threshold of credibility. In addition, the Construction

Contracts Act 2002 provides that there is no contracting out of its provisions: section 12.

 

 

[33] Accordingly, I find that valid 'payment claims' have been served. No

payment schedule has been received in response. The debt has crystallised.

 

 

[34] I am satisfied that there is no reasonably arguabIe defence and that

summary judgment should be given. Accordingly, there is summary judgment

against the defendant for -

 

$46,236.90 plus GST in respect of the contract at 4 Dallan Place, Albany and

 

$35,872.5 plus GST in respect to the contract at 6 Dallan Place, Albany.

 

Interest is sought and allowed at the rate of 7.5% in respect of 4 Dallan Place at

$1,130.50 and in respect of 6 Dallan Place in the sum of $877.03 up to the date

of hearing. Interest is allowed at the same rate to the date of judgment.

 

 

[35] The plaintiff will have actual and reasonable costs, including counsel's travel

expenses pursuant: to s23 (2)(a)(ii) of the Construction Contracts Act.

 

 

[36] Counsel are to endeavour to agree on costs and disbursements but in the

absence of agreement, are to file and serve memoranda The plaintiff will file and

serve its memorandum on or by 4pm on the 24th March 2004.' The defendant will

respond on or by 4pm on 1st April 2004.

 

 

[37] My thanks to counsel for their helpful submissions.

 

 

Reserved Decision of D M Wilson QC