QC CONSTRUCTION LIMITED V APT TILING LIMITED HC AK CIV 2006-404-00676 [2006] NZHC 537 (19 May 2006)
IN THE HIGH COURT OF NEW ZEALAND
AUCKLAND REGISTRY
CIV 2006-404-00676
IN THE MATTER OF Section 290 Companies Act 1993
BETWEEN QC CONSTRUCTION LIMITED
Applicant
AND APT TILING LIMITED
Respondent
AND CIV 2006-404-0086
BETWEEN QC CONSTRUCTION LIMITED
Applicant
AND APT TILING LIMITED
Respondent
Hearing: 15 May 2006
Appearances: W A McCartney for Applicant
J Noble for Respondent
Judgment: 19 May 2006 at 4.40 p.m.
JUDGMENT OF ASSOCIATE JUDGE J P DOOGUE
Counsel: W A McCartney, P O Box 4420,
Shortland Street, Auckland
Solicitors: Carson & Co, P O Box 37403, Parnell, Auckland
Boyle Mathieson, P O Box 21-640, Waitakere City
QC CONSTRUCTION LIMITED V APT TILING LIMITED HC AK CIV 2006-404-00676 19 May 2006
[1] The applicant has filed an application to set aside statutory demand pursuant
to s 290 of the Companies Act 1993.
[2] The application was originally made on the grounds set out in s 290(4)(b) of
the Act. Mr McCartney told me however that the company now accepts that it is
unable to succeed on that basis. The company, in other words, accepts that the
position is as the judgment creditor has stated it to be. The judgment creditor says
that it made a number of payment claims within the meaning of s 20 of the
Construction Contracts Act 2002. In each case, the judgment debtor issued a
payment schedule showing an amount that the judgment debtor proposed
to pay to the judgment creditor. Those sums were the full amounts claimed in the payment
claims. The consequence is that in terms of s 24 of the Act the judgement credit is
able to recover the debt due in any Court within the meaning of s 24(2)(a).
[3] Further, s 79 of the CCA prevents the judgment debtor from raising any
counter-claim in any proceedings for the recovery of the debt except where judgment
has been entered for the counter-claim or where there is no dispute between the parties in relation to the claim.
[4] Section 79 would appear to apply to the present proceedings and accordingly,
the judgement debtor is unable to raise against the claim of the judgment creditor any
entitlement to a cross-demand counter-claim or anything of that nature arising out of
the allegedly defective work done by the judgment creditor.
[5] Accordingly the judgment creditor concedes, and properly in my view, that it
has to comply with the statutory demand in one way or another and that the statutory
demand cannot be set aside.
[6] Mr McCartney for the judgement debtor submitted that the appropriate
course was to allow the judgment debtor time pursuant to s 291 of the Act. Mr
McCartney said that if such an order was made then the judgment debtor would
either pay the money claimed in or give security for it.
[7] Mr Noble for the judgement creditor said that his client had already waited too
long for payment. He submitted that the appropriate order I should make was under s 291(1)(b) dismissing the application forthwith making an order putting the
company into liquidation.
[8] I am not prepared to make an order putting the company into liquidation.
While I agree that there has been unnecessary delay, it would appear that the
judgment debtor did not initially apprehend what the affect of the provisions of the
CCA were in that they constituted a bar to the judgment debtor moving to set aside
the statutory demand on the basis that it has a cross-demand or counter-claim. I
accept that the judgement debtor was acting bona fide (if mistakenly) in bringing the
proceedings in the first place. As well, there is some evidence before the Court
which would indicate that the company will be able to pay the debt. Finally, an
order under s 291(1)(b) will necessarily be made in the absence of any knowledge of
possible prejudice to third parties: Gameline of New Zealand v TV3 Network
Services Limited HC CHCH M188-96 12 July 1996. Because of this last factor, and
because I am not persuaded that there is great urgency in placing the company in
liquidation, I would prefer to proceed by way of s 291(1)(a).
[9] Therefore I direct that the applicant is to pay the debt within 14 days from
today and that in default of payment, the company may make an application to put
the company into liquidation.
[10] The respondent has been successful on its application and it shall have costs
on a 2B basis together with disbursements to be fixed by the registrar.
J.P. Doogue
Associate Judge