TOP END HOMES LIMITED V SALEM LIMITED HC WHA CIV 2005-488-000332 [19 July 2005]

IN THE HIGH COURT OF NEW ZEALAND

WHANGAREI REGISTRY CIV 2005-488-000332

 

BETWEEN TOP END HOMES LIMITED

Plaintiff

 

AND SALEM LIMITED

Defendant

 

Hearing: 19 July 2005

 

Appearances: Mr R M Bell for Plaintiff

Mr W W Peters for Defendant

 

Judgment: 19 July 2005

 

ORAL JUDGMENT OF VENNING J

 

Solicitors: Webb Ross Johnson, Whangarei

Thomson Wilson, Whangarei

 

[1] The plaintiff seeks summary judgment against the defendant in the sum of

$279,687.56 together with interest and costs.

 

 

Background

 

[2] The plaintiff is a builder. The plaintiff carried out work on the defendant’s

property known as the Money Factory site in Whangarei, pursuant to a construction

contract made between the parties on 7 July 2004. The defendant has made

payments under the contract totalling $920,477.13. In early February 2005 the

plaintiff delivered a payment claim under the Construction Contracts Act to the

defendant. In that claim the plaintiff sought payment of the $279,687.56. It was a

final claim.

 

 

[3] The defendant did not pay that sum. Nor did the defendant serve a payment

schedule under the Construction Contracts Act within the time specified in the Act.

The defendant did purport to serve a payment schedule on 24 March 2005.

 

 

[4] The defendant opposes the application for summary judgment. It says that it

has a complete defence and set-off/counterclaim to the plaintiff’s claim arising from

the actions of the plaintiff.

 

 

Principles

 

[5] The principles relating to summary judgment are well established. It is for

the plaintiff to satisfy the Court that the defendant does not have a reasonably

arguable defence to the plaintiff’s claim: Pemberton v Chappel [1987] 1 NZLR 1.

 

 

The Construction Contracts Act

 

[6] The plaintiff relies upon the provisions of the Construction Contracts Act.

 

 

[7] That Act came into force on 1 April 2003. The purpose of the Act is stated to

be:

- to facilitate regular and timely payments;

- to provide for a speedy resolution of disputes; and

- to provide remedies for recovery of payments due under construction

contracts.

 

 

[8] The Act enables a contractor to serve a payment claim for progress payments

(defined to include one-off or final payments) in accordance with s 20 of the Act:

s 16.

 

 

[9] A progress payment is due and payable 20 working days after the payment

claim is served in the absence of other agreement between the parties – s 18. The

payment claim must

- be in writing;

- contain sufficient details to identify the construction contract to which it

relates;

- identify the construction work and the relevant period to which the progress

payment relates;

- indicate a claimed amount and the due date for payment;

- indicate the manner in which the payee calculated the claimed amount;

- state that it is made under the Act.

 

 

[10] If a payer wishes to challenge the payment claim or take issue with it then a

payment schedule must be issued: s 21. The payment schedule must:

- be in writing; and

- identify the payment claim to which it relates; and

- indicate the scheduled amount.

 

 

[11] The scheduled amount is the amount of the progress payment that the payer

proposes to pay to the payee in response to the payment claim.

 

 

[12] By s 22 of the Act the payer becomes liable to pay the claimed amount on the

due date for the progress payment to which the payment claim relates if:

- the payee serves a payment claim on a payer; and

- the payer does not provide a payment schedule to the payee within the time

required by the contract or by default within 20 working days after the

payment claim is served – s 22 (b)(ii).

 

 

[13] If a payer becomes liable to pay the claimed amount under s 22 by failing to

provide a payment schedule and fails to pay the whole amount in the payment claim,

then the payee may recover from the payer as a debt due to it the unpaid portion of

the claimed amount and the actual and reasonable costs of recovery – s 23 (2).

 

 

Application in this case

 

[14] In this case on 3 February 2005 the solicitors acting for the plaintiff wrote to

the defendant enclosing a payment claim for the $279,687.56, the subject of the

present proceedings. The letter and accompanying schedules were clearly in writing.

The letter and schedules contained sufficient details to identify the construction

contract, the construction work and the relevant period to which the progress claim

related. The letter set out that the claim was for: construction work carried out in building the offices for the Ministry of Education lease at the Money Factory site at Awaroa River Road between July 2004 and December 2004. It went on to record that the schedule took into account all the work up until 31 December 2004. As noted the letter and claim included a schedule which set out in detail how the amount claimed was made up. The letter also recorded that the time for payment was 20 working days after receipt. Finally, the letter stated that the claim was a payment claim under the Construction Contracts Act. The letter and accompanying schedule was a payment claim for the purposes of the Construction Contracts Act.

 

 

Service

 

[15] The evidence of Mr McGonagle, a director of the plaintiff company, is that

the claim was served on the defendant in the following ways:

company;

note there is an acknowledgement of receipt of the document that day on behalf of the defendant; and

- on 11 February by personal service on Mr Kim at the work site.

 

 

[16] I note that s 80 of the Act provides that service may be effected by:

- the notice or document being delivered; or

- the notice of document being left at a usual or last known place of business;

- the notice or document being posted in a letter addressed to the payer; and

- the notice or document sent in a prescribed manner if any.

 

 

[17] The evidence before this Court incorporates affidavits by both parties in

related proceedings under the Companies Act 1993. In one affidavit Mr Kim a

director of the defendant has confirmed receipt of the payment claim on or about 3

February 2005. In any event and to put the matter beyond doubt the document was

served at the very latest by 7 February when it was delivered to the registered office

of the defendant company, receipt of which was acknowledged: ss 387 and 388 of

the Companies Act 1993.

 

 

The defendant’s response

 

[18] The 20 working days, being the default period prescribed in the Act for a

payment schedule response expired then at the latest on 7 March 2005. The

evidence before the Court is that the first document purporting to be a payment

schedule on behalf of the defendant under s 21 of the Act was the defendant’s

solicitor’s letter of 24 March 2005. That letter is well outside the default period of

20 working days prescribed in the Construction Contracts Act. There is no

suggestion that any extended period was agreed to by the parties in the construction

contract. Indeed if anything the contract seems to have contemplated claims being

responded to within seven working days. However, for present purposes the plaintiff

relies on the default provision of 20 working days in the Act.

 

 

[19] The consequences of the defendant’s failure to respond within the time

prescribed by the Act is that the defendant became liable to pay the claimed amount

on the expiry of the 20 working days: s 22. The defendant has failed to pay and in

accordance with s 23 (2) of Act the plaintiff may now recover as a debt due to it the

entire unpaid portion of the claimed amount from the defendant together with actual

and reasonable costs of recovery.

 

 

The defence

 

[20] The notice of opposition filed on behalf of the defendant does not provide

particulars of the defence. It simply alleges generally that the defendant has a

complete defence to the claim and that the plaintiff’s claim is an abuse of the

summary judgment procedure. It does not provide any further particulars as is

required by r 244 (3).

 

 

[21] However, in submission Mr Peters expanded on the nature of the defence. In

summary it is that summary judgment ought not to be entered because the defendant

has in respect of the plaintiff’s claim a “complete defence” and equally importantly

has a set-off/counterclaim as against the plaintiff and that both the claim by the

plaintiff in these proceedings and the set-off/counterclaim involve material issues of

fact which should be considered and determined after the presentation of viva voce

evidence.

 

 

Discussion

 

[22] On behalf of the defendant it was accepted there was a contractual relationship between the plaintiff and defendant but it was submitted that the nature of the contractual relationship was contained in an earlier document rather than that

relied on by the plaintiff. On 10 May 2004 Mr McGonagle trading as D & D

Builders forwarded a quote to the defendant for construction work to be carried out

in relation to the Money Factory at Whangarei. At that time the quotation was for a

fixed price contract of $589,000, excluding GST. The defendant’s case is based on

that document being the operative contractual document. However, the evidence

satisfies me that that document did not form the basis of the contractual agreement

between the parties and is not the construction contract for the purposes of the Act.

As Mr McGonagle deposed he had further discussions with Mr Kim after that

quotation was provided. The proposed tenant of the premises required further work

to be carried out. The further discussions led to agreement that the project would

proceed on the basis of a cost plus contract. That cost plus contract was recorded in

written form as an agreement between the plaintiff Top End Homes Limited and the

defendant Salem Limited. It is the cost plus contract which forms the basis of the

plaintiff’s claim and which is the construction contract for the purposes of the Act.

 

 

[23] That cost plus contract agreement clearly post-dates the earlier quotation of

10 May 2004. As at 10 May 2004 Top End Homes Limited had not been

incorporated. The agreement on the cost plus basis was clearly made between the

plaintiff and defendant. It was executed on behalf of the plaintiff by its directors Mr

McGonagle and Mr Pickerill. It was executed on behalf of the defendant by Mr Kim.

 

 

[24] The cost plus contract is of a completely different nature and, as counsel

submitted, is the antithesis of a fixed price contract. I also note that the defendant

has paid in excess of $970,000 already. That is evidence on the part of the defendant

itself that it did not consider the earlier fixed price contract for $589,000 plus GST

was the basis for the contract. It would not have paid up to $970,000 if it considered

it had a fixed price contract for a substantially lesser sum.

 

 

[25] I find as a matter of fact that the relevant agreement was the contract

agreement between Top End Homes Limited and Salem Limited as set out on the

cost plus basis. As discussed with counsel I do not consider the fact that that

contract expressly stated to be between those parties was made on a letterhead that

refers to D & D Builders to be material. Given the nature of the parties to this

contract I do not consider that to be of any significance at all.

 

 

[26] The position then is that the defendant acknowledges there is a contractual

relationship between the parties. This Court has found that the contractual

relationship is the written cost plus contract. The defendant faces the position that

the payment claim issued under the Act was issued pursuant to that agreement. It

was not responded to by way of payment schedule within the time as required by the

Act.

 

 

[27] The substance of the defence, namely that the contractual document was a

quotation has been found as a matter of fact against the defendant. Apart from that

issue then absent any challenge to the quantum of the plaintiff’s claim by way of

payment schedule in the manner required by the Act the other matters raised by the

defendant in the letter of 24 March 1995 effectively amount to a set-off or

counterclaim. The provisions of s 79 of the Act make it clear that a party in the

position of the defendant can only raise a set-off in very limited circumstances in

proceedings for the recovery of debt pursuant to s 23. Section 79 provides:

 

79 Proceedings for recovery of debt not affected by counterclaim,

set-off, or cross-demand

 

In any proceedings for the recovery of a debt under section 23 or section 24

or section 59, the court must not give effect to any counterclaim, set-off, or

cross-demand raised by any party to those proceedings other than a set-off of

a liquidated amount if—

(a) judgment has been entered for that amount; or

(b) there is not in fact any dispute between the parties in relation to the

claim for that amount.

 

 

[28] The section prevents the Court from giving effect to any counterclaim, set-off

or cross demand raised by the party in the position of the defendant in proceedings

such as these. The only exception is that if there is a set-off of a liquidated amount

in relation to which either judgment has been entered or there is not any dispute

between the parties in relation to it. Neither of those circumstances apply in the

present case.

 

 

[29] With respect to the matters advanced on behalf of the defendant in my view

they are based on a misapprehension of the force and effect of the Construction

Contracts Act. The Act represents a change in the approach to the recovery of

claims by contractors. The previous authorities referred to and relied on by

Mr Peters for the defendant: Hempseed v Durham Developments Limited [1998] 3

NZLR 265 and Savory Holdings Ltd v Royal Oak Mall Ltd [1993] 1 NZLR 12 are

not applicable to claims based on the statutory provisions of the Construction

Contracts Act. The Act was recently considered by the Court of Appeal in George

Developments Limited v Canam Construction Limited. In that case the Court of

Appeal observed that:

[41] We are satisfied that the necessary analysis [whether the item of the

payment claim was adequately identified as such] must be undertaken with

the purpose of the Act in mind. The purpose provision of the Act includes

the fact that the Act was "to facilitate regular and timely payments between

the parties to a construction contract". The importance of such regular and

timely payments is well recognised. Lord Denning (quoted in Gilbert-Ash

(Northern) Ltd v Modern Engineering (Bristol) Ltd [1973] 3 All ER 195, 214

(HL) Lord Diplock) said: "There must be a "cashflow" in the building trade.

It is the very life blood of the enterprise".

 

 

[30] Given that clear statement as to the purpose of the Act and the provisions of

s 79 this Court can not take into account any potential counterclaim, set-off or cross

demand the defendant may wish to raise against the plaintiff. A fortiori it follows

that where the defence is a challenge to the quantum of the claim the appropriate

way for that to be challenged is by means of the payment schedule process.

 

 

[31] Where as here the Court has found there is sufficient evidence to confirm the

construction contract and the plaintiff has otherwise complied with the provisions of

the Act then prima facie the plaintiff is entitled to summary judgment in reliance

upon ss 22 and 23 of the Act.

 

 

The discretion to decline summary judgment

 

[32] Towards the end of his submissions Mr Peters recognised that the Court may

come to that view. He submitted that even if the Court came to that view the Court

should exercise its discretion against entering summary judgment in this case. He

invited the Court to consider what the position might be after judgment in that there

were issues between the parties that may still need to be resolved. He submitted they

should appropriately be resolved by arbitration. He also suggested that there would

be no point in the plaintiff seeking to enforce any judgment by way of issuing

liquidation proceedings as the defendant was solvent and would be able to defend

any such proceeding.

 

 

[33] I acknowledge there may be some practical force in aspects of Mr Peters’

submission, however, as the Court has acknowledged where a plaintiff is otherwise

prima facie entitled to summary judgment it will be rare for the Court to exercise

discretion against entering summary judgment: Berg v Anglo Pacific International

(1988) Ltd (1989) 1 PRNZ 713, 717; Dominion Breweries Ltd v countrywide

Banking Corporation Ltd (CA 314/91, 18 August 1992). It is not for this Court at

this time to second guess what steps the plaintiff may or may not take in terms of

executing the judgment which it is otherwise entitled to. I am not minded to exercise

the discretion against the plaintiff in this case.

 

 

Conclusion

 

[34] The result is that I accept the submissions for the plaintiff that it is entitled to

summary judgment. The plaintiff satisfies me the defendant has no reasonably

arguable defence. I enter summary judgment for the plaintiff against the defendant

in the sum of $279,687.56 together with interest at the Judicature Act rate to today’s

date of $9,540,03 and costs as contemplated by s 23 according to scale in the total

sum of $8,390.00, in total the sum of $297,617.59.

 

 

G J Venning J