Thiess Pty Ltd & Anor v Zurich Specialties London Ltd & Anor [2009] NSWCA 47 (3 March 2009)

 

Last Updated: 18 March 2009

 

NEW SOUTH WALES COURT OF APPEAL

 

CITATION:

Thiess Pty Ltd & Anor v Zurich Specialties London Ltd & Anor [2009] NSWCA 47

 

FILE NUMBER(S):

40316/08

 

HEARING DATE(S):

3 March 2009

 

EX TEMPORE DATE:

3 March 2009

 

PARTIES:

Thiess Pty Ltd (First Appellant)

John Holland Pty Ltd (Second Appellant)

Zurich Specialties London Ltd (First Respondent)

Swiss re International SE (Second Respondent)

 

JUDGMENT OF:

Allsop P Macfarlan JA Sackville AJA

 

LOWER COURT JURISDICTION:

Supreme Court - Equity Division

 

LOWER COURT FILE NUMBER(S):

SC 55090/08

LOWER COURT JUDICIAL OFFICER:

Bergin J

 

LOWER COURT DATE OF DECISION:

25 September 2008

 

LOWER COURT MEDIUM NEUTRAL CITATION:

Zurich Specialties London Ltd v Thiess Pty Ltd [2008] NSWSC 1010

 

COUNSEL:

M Christie/V Culkoff (Appellants)

J E Marshall SC/ D S Weinberger (Respondents)

 

SOLICITORS:

Herbert Geer (Appellants)

Wootton & Kearner (Respondents)

 

CATCHWORDS:

BUILDING AND ENGINEERING CONTRACTS - Building and Construction Industry Security of Payment Act 1999 - whether Construction Risks Insurance Policy contained a "construction contract"

 

INSURANCE - Construction Risks Insurance Policy - whether imposed an obligation on insured to perform construction work - whether obligation to take "reasonable precautions" simply a condition precedent to insurer's liability or whether it also gave rise to an enforceable promise to take those precautions.

 

LEGISLATION CITED:

Building and Construction Industry Security of Payment Act 1999

 

CATEGORY:

Principal judgment

 

CASES CITED:

CGU Insurance v Porthouse [2008] HCA 30 ; (2008) 235 CLR 103

McCann v Switzerland Insurance Australia Ltd [2000] HCA 65 ; (2000) 203 CLR 579

 

TEXTS CITED:

 

DECISION:

Appeal dismissed with costs.

 

JUDGMENT:

IN THE SUPREME COURT

OF NEW SOUTH WALES

COURT OF APPEAL

CA 40316/08

SC 55090/08

ALLSOP P

MACFARLAN JA

SACKVILLE AJA

TUESDAY 3 MARCH 2009

THIESS PTY LTD & ANOR v ZURICH SPECIALTIES LONDON LTD & ANOR

 

Judgment

 

1 ALLSOP P : I will ask Macfarlan JA to give the first judgment.

 

2 MACFARLAN JA : This is an appeal from a decision of Bergin J sitting in the Technology and Construction List of the Equity Division. The circumstances in which the proceedings came before her Honour are fully described by her Honour in her judgment for which the reference is [2008] NSWSC 1010.

 

3 The issue determined by her Honour was a narrow one, namely, whether the Construction Risks Insurance Policy issued by the respondents and others to the appellants in relation to the construction of the Lane Cove Tunnel contains a “construction contract” within the meaning of the Building and Construction Industry Security of Payment Act 1999 to which I will refer as “the Act”.

 

4 The appellants assert that it does and that they are able to avail themselves of the provisions of the Act to obtain progress payments from the respondents in respect of construction work done by them following upon the collapse of part of the tunnel on 2 November 2005.

 

5 The definition of “construction contract” in s 4 of the Act is as follows:

 

“Construction contract means a contract or other arrangement under which one party undertakes to carry out construction work, or to supply related goods and services, for another party”.

 

6 The only other provision of the Act to which reference need be made is s 7(2)(a) , the relevant parts of which read as follows:

 

“(2) This Act does not apply to:

 

(a) a construction contract that forms part of ... a contract of insurance under which a recognised financial institution undertakes:

...

 

(iii) to provide an indemnity with respect to construction work carried out, or related goods and serves supplied, under the construction contract, ...”

 

7 The appellants contend that this provision contains a recognition by the Act that there are some circumstances in which an insurance policy might contain a construction contract. The respondents did not submit otherwise and the proposition in my view is clearly correct but does not resolve the question that arises on this appeal.

 

8 Relevant provisions of the Construction Risks Insurance Policy are as follows:

 

“18. Project Deed Compliance

 

Insurers agree that they are aware of the obligation imposed on Insureds #1 and #3 by the project deed and other contracts for the Project that specifies that Insureds #1 and #3 must – following loss or damage to the Subject Matter Insured for Section I:

 

(a) subject to allowing reasonable time for inspection by Insurers, take immediate steps to clear any debris and begin initial repair work;

 

(b) promptly consult with Insured #2 and carry out such steps as are necessary to ensure the prompt repair or replacement of the Subject Matter Insured so that it complies with contractual requirements, disruption of the Project is minimised and Insureds #1 and #3 continue to comply with their contractual obligations to the greatest degree possible.

Notwithstanding the above, the Insured shall take and cause to be taken all reasonable precautions to safeguard the Subject Matter Insured and to prevent loss or damage. The Insured shall also afford reasonable facilities for Insurers’ representatives to examine any of the Subject Matter Insured.

 

19. Due Observance of Policy Terms

 

The due observance and fulfilment of the terms, Conditions and limitations of this Policy as far as they relate to anything to be done or complied with by the Insured shall be conditions precedent to any liability of the Insurers to make payment under this Policy.

 

“General Conditions

 

3. Advice of Loss

 

(a) In the event of loss or damage which may give rise to a claim under this Policy the Insured shall:

 

(i) give advice thereof to the Insurers as soon as possible;

 

(ii) take all reasonable steps to protect the Subject Matter Insured from further loss or damage.”

 

Memoranda Applicable to Section I

 

6. Sue and Labour

 

It is agreed that in the event of actual or imminent damage to the Subject Matter Insured the Insurers will pay the reasonable costs of emergency action in order to minimise or prevent damage to the Subject Matter Insured.

 

Provided always that:

 

(a) Insurers shall not be expected to pay any amount in excess of that which they would reasonably have been expected to pay in settlement of actual damage had such measures not have been taken.

 

(b) the maximum sum payable by Insurers under this Memorandum shall not exceed $10,000,000 for any one Occurrence or such higher amount as insurers may approve.

 

For the purposes of this Memorandum, “imminent” shall mean within fourteen (14) days of discovery.”

 

9 The submission of the appellants at first instance and on appeal was that cl 18 of the policy constituted a separate construction contract between them and the respondents to carry out construction work. They said that the obligation under cl 18 to take all reasonable precautions to safeguard the subject matter insured and to prevent loss or damage would in certain circumstances obviously include the need to carry out construction work.

 

10 On appeal they also referred to cl 3 which is quoted above and which requires the insurer to take all reasonable steps to protect the subject matter insured. They also referred to the sue and labour clause in cl 6 of the memorandum, which I have also set out earlier. Neither of these clauses in my view provides any material assistance to the appellants’ submissions.

 

11 The primary judge rejected the appellants’ submission that the insurance policy contained a construction contract. Her Honour’s reasons were expressed as follows

 

“15 The first paragraph of clause 18 is an agreement by the insurers that they are aware of the obligations imposed on the defendants by the project deed and other contracts for the Project following loss or damage. The second paragraph of clause 18 commencing “notwithstanding” imposes on the defendants the obligation to take the reasonable precautions. The clause must be read to give effect to the commercial purpose of the contract: Legal & General Insurance Australia Ltd v Eather (1986) 6 NSWLR 390 at 405 per McHugh JA (as his Honour then was). The commercial purpose of this Policy was to provide indemnity for the insured on the terms and conditions included in the Policy. The second paragraph of clause 18 was the imposition of a condition on the insured, which had to be satisfied prior to indemnity being available. It was not an agreement by the insured to carry out construction work for the insurer, but an agreement by the insured that in carrying out the construction work for the principals/owners they had to do so in a particular manner, that is, taking the reasonable precautions, in order to qualify for indemnity under the Policy.”

 

12 I agree with her Honour’s conclusion and with her reasons. As is evident from her Honour’s reasons, the critical question is whether the requirement in cl 18 for the insured to take “reasonable precautions” for the purpose specified simply constitutes a condition precedent to the insured’s right to indemnity under the policy or whether instead, or as well, it embodies a contractual promise by the insured to take the steps.

 

13 The proper approach to the construction of an insurance policy was identified in the following statement of Gleeson CJ in McCann v Switzerland Insurance Australia Ltd [2000] HCA 65 ; (2000) 203 CLR 579 at [22] affirmed by the High Court in CGU Insurance v Porthouse [2008] HCA 30 ; (2008) 235 CLR 103 at [43] :

 

“A policy of insurance, even one required by statute, is a commercial contract and should be given a businesslike interpretation. Interpreting a commercial document requires attention to the language used by the parties, the commercial circumstances which the document addresses, and the objects which it is intended to secure.”

 

14 As the parties agreed, the commercial purpose of the insurance policy here in question is to provide indemnity against certain loss and damage. The commercial purpose is not to enable the insurers to procure the performance of construction work.

 

15 The requirement to take reasonable precautions which admittedly might in certain circumstances involve the performance of construction work is designed to protect the insurers by limiting their obligations to indemnify the insureds. This role is made clear by cl 19 which immediately follows the clause relied upon by the appellants. In that clause compliance with the terms, conditions and limitations of the policy is made a condition precedent to any liability of the insurers to make payment under the policy.

 

16 Whether there is a promise, or to use the expression used in the definition of “construction contract” in the Act, undertaking to carry out construction work can in my view be tested by asking whether the insurers could sue the insureds for damages if the insureds failed to take reasonable precautions as required by cl 18. Clearly, in my view, they could not. That would not be in conformity with the commercial purpose of the policy and is not dictated by any language used by the parties.

 

17 The requirement of reasonable precautions is a condition of the insurer’s obligation to indemnify, not a promise or undertaking by the insured to take those steps. In my view the appeal should be dismissed with costs.

 

18 ALLSOP P : I agree.

 

19 SACKVILLE AJA : I also agree.

 

20 ALLSOP P : The orders of the court are that the appeal be dismissed with costs.

 

**********

 

LAST UPDATED:

16 March 2009