Queensland Bulk Water Supply Authority v. McDonald Keen Group P/L & Anor [2009] QSC 165 (20 July 2009)
Last Updated: 21 July 2009
SUPREME COURT OF QUEENSLAND
CITATION: |
Queensland Bulk Water Supply Authority v McDonald Keen Group P/L & Anor [2009] QSC 165 |
PARTIES: |
QUEENSLAND BULK WATER SUPPLY AUTHORITY ABN 75 450 239 876 (Applicant) v MCDONALD KEEN GROUP PTY LTD (IN LIQUIDATION) ACN 090 921 949 (First Respondent) and PHILIP DAVENPORT (Second Respondent) |
FILE NO: |
BS 9365 of 2008 |
DIVISION: |
Trial Division |
PROCEEDING: |
Application |
ORIGINATING COURT: |
Supreme Court at Brisbane |
DELIVERED ON: |
20 July 2009 |
DELIVERED AT: |
Brisbane |
HEARING DATE: |
1, 2 June 2009 |
JUDGE: |
P Lyons J |
ORDER: |
|
CATCHWORDS: |
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – OTHER MATTERS – Where construction contract to undertake rock excavation – Where the Second Respondent made an adjudication decision on a claim under the Building & Construction Industry Payments Act 2004 (Qld) ( Payments Act) – Where the Applicant has applied for a declaration that the adjudicator’s decision is void on the basis that there was no evidence on which the adjudicator could determine the amount of the claim – Whether the adjudicator failed to comply with the statutory provisions of the Payments Act – Whether the adjudicator failed to accord natural justice in the decision making process –– Whether the adjudicator erred in taking into account a Facsimile in forming part of the decision about the contract.
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – OTHER MATTERS – Where the Applicant seeks an order that the judgment entered by the First Respondent against the Applicant be set aside – Where in the alternative, the Applicant seeks a stay of execution of that judgment – whether there is a power to grant a stay – whether the First Respondent should have access to moneys paid into court before the resolution of these proceedings.
Building & Construction Industry Payments Act 2004 (Qld) , ss 21, 22, 23, 24, 25, 26, 27, 30, 31, 99 and 100
Judicial Review Act 1991 (Qld)
Administrative Decisions (Judicial Reviews) Act 1977 (Cth)
Migration Act 1958 (Cth) , s474
Uniform Civil Procedure Rules 1999 (Qld), r 800
Associated Provincial Picture House Ltd v Wednesbury Corporation [1948] 1 KB 223, considered
BMD Major Projects Pty Ltd v Victorian Urban Development Authority [2007] VSC 409 , cited
Brewarrina Shire Council v Beckhaus Civil Pty Ltd [2003] NSWCA 4 ; (2003) 56 NSWLR 576 , cited
Brodyn Pty Ltd t/a Time Cost and Quality v Davenport [2004] NSWCA 394 ; (2004) 61 NSWLR 421 , considered
Downer Construction (Australia) Pty Ltd v Energy Australia [2007] NSWCA 49 ; (2007) 69 NSWLR 72 , considered
Grosvenor Constructions (NSW) Pty Limited (in Administration ) v Musico [2004] NSWSC 344 , considered
Halkat Electrical Contractors Pty Ltd v Holmwood Holdings Pty Ltd [2007] NSWCA 32 , considered
Halkat Electrical Contractors v Holmwood Holdings Pty Ltd [2006] NSWCA 125 , considered
Holmwood Holdings v Halkat Electrical Contractors [2005] NSWSC 1129 , considered
John Holland Pty Ltd v Roads and Traffic Authority of New Minister for Commerce v Contrax Plumbing (NSW) Pty Ltd [2007] NSWCA 19 , cited
Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355, applied
Timwin Construction Pty Ltd v Façade Innovation Pty Ltd [2005] NSWSC 548 , considered
|
COUNSEL: |
R A Holt SC with P D Tucker for the Applicant J K Bond SC with M Ambrose for the Respondents
|
SOLICITORS: |
Minter Ellison for the Applicant Mullins Lawyers for the Respondents
|
[1] P Lyons J: On 20 June 2008, the Second Respondent made an adjudication decision on a claim under the Building & Construction Industry Payments Act 2004 (Qld) (the Payments Act ) by McDonald Keen Group Pty Ltd ( MKG ) against the Caloundra-Maroochydore Water Supply Board (now Queensland Bulk Water Supply Authority – ( QBWSA )) in an amount of $11,122,645.61. QBWSA contends that the decision was invalid, on a number of bases including a failure by the Second Respondent to comply with the statutory provisions of the Payments Act which conferred the adjudication power on him; a failure to accord natural justice; and the fact that there was no evidence to justify the amount awarded. It seeks a declaration that the adjudication decision is void, and other relief.
Background
[2] In 2006, the Caloundra-Maroochy Water Supply Board was undertaking the construction of a pipeline some 27 kilometres in length in the Caloundra region. On 27 February 2008, by a Transfer Notice given pursuant to s 67(1) of the Water Act 2000 (Qld), its assets and liabilities were transferred to QBWSA . For convenience, the Caloundra-Maroochy Water Supply Board will also be referred to as QBWSA .
[3] QBWSA called for tenders for the construction of the pipeline, which involved excavation, the laying of the pipe, and the placing of backfill. A geotechnical report relating to land where the pipeline was to be constructed was provided to tenderers. It showed that some 190 test pits had been excavated with machinery, and that in 126 of those, rock had been encountered. The geotechnical report included the following statement:
“In some areas however, where rock is massive with few joints or defects, production rates will be very low and blasting may be required. It is not possible to identify such areas from the investigations undertaken.”
[4] MKG lodged a tender on 11 April 2006. With respect to excavation in rock, the tender included a provisional sum of $40,000.
[5] On 13 April 2006, JWP (the design engineers and the Superintendent of the project) sent a facsimile to MKG , commenting on its tender ( the Facsimile ). The Facsimile sought further information, and identified two respects in which it was said that the tender was non-conforming. That which related to the provisional sum for excavation was as follows:
“2. A provisional sum for item 11 (which related to excavation in rock) in the Bill of Quantities;
Adequate information was provided in the documentation to allow this activity to be priced as a lump sum .”
[6] MKG responded on 21 April 2006. With respect to excavation in rock, the response included the following:
“The express condition of Item 11 being a Provisional Sum can be deleted. The allowance of $30,000 for rock in this Item remains as part of our Lump Sum.”
[7] QBWSA and MKG entered into a written contract dated 13 June 2006. It expressly identified the documents which comprised the contract, and included the tender of 11 April 2006, and the further communication of 21 April 2006, but did not refer to the Facsimile. It included AS 2124-1992, clause 12 of which dealt with latent site conditions.
[8] In the course of the project, substantial quantities of hard rock were encountered by MKG . These became the subject of a series of claims based on clause 12. Ultimately, they were superseded by a Payment Claim under the Payments Act , dated 4 April 2008, the claim again being based on clause 12. QBWSA provided a Payment Schedule dated 18 April 2008. This resulted in an adjudication application on 2 June 2008, an adjudication response on 11 June 2008, and an adjudication decision on 20 June 2008.
[9] The adjudication decision identified the Adjudicated Amount as $11,122,645.61 and the due date for payment as 2 May 2008.
[10] MKG has been placed in liquidation. The liquidator entered judgment under s 31 of the Payments Act on the basis of a certificate from Adjudicate Today , the Nominating Authority.
[11] As mentioned, QBWSA has applied for a declaration that the decision of the Second Respondent is void. By an amendment to the application made on the first day of the hearing, it also seeks an order that the judgment entered by MKG against QBWSA be set aside. In the alternative it seeks a stay of execution of that judgment.
Statutory background
[12] Part 3 of the Payments Act contains a procedure for recovering progress payments. It includes provisions for the adjudication of disputes between parties to a building contract. Under s 21, a claimant may apply for adjudication of a Payment Claim in certain circumstances. Under s 23, an adjudicator may be appointed in respect of the Adjudication Application. Provision is then made under s 24 for an Adjudication Response. A period of 10 business days is fixed by s 25(3) for deciding the adjudication application, unless the parties agree to an extension of that period.
[13] Section 26 deals with the adjudicator’s decision. In part, it requires the adjudicator to decide the amount of the progress payment to be paid to the claimant. Subsection (2) of s 26 states:
“( 2) In deciding an adjudication application, the adjudicator is to consider the following matters only—
(a) the provisions of this Act and, to the extent they are relevant, the provisions of the Queensland Building Services Authority Act 1991 (Qld), part 4A ;
(b) the provisions of the construction contract from which the application arose;
(c) the payment claim to which the application relates together,with all submissions, including relevant documentation, that have been properly made by the claimant in support of the claim;
(d) the payment schedule, if any, to which the application relates, together with all submissions, including relevant documentation, that have been properly made by the respondent in support of the schedule;
(e) the results of any inspection carried out by the adjudicator of any matter to which the claim relates.”
[14] Section 27 then requires payment of the adjudicated amount. Under s 30 , if the amount is not paid, the claimant may ask the authorised nominating authority to whom the adjudication application was made to provide an adjudication certificate. Under s 31 , an adjudication certificate may be filed as a judgment for a debt, and may be enforced, in a court of competent jurisdiction.
[15] Under s 99 , the provisions of the Act may not be excluded by agreement between the parties. Section 100 of that Act is in the following terms:
“ 100 Effect of pt 3 on civil proceedings
(1) Subject to section 99, nothing in part 3 affects any right that a party to a construction contract—
(a) may have under the contract; or
(b) may have under part 2 in relation to the contract; or
(c) may have apart from this Act in relation to anything done or omitted to be done under the contract.
(2) Nothing done under or for part 3 affects any civil proceedings arising under a construction contract, whether under part 3 or otherwise, except as provided by subsection (3).
(3) In any proceedings before a court or tribunal in relation to any matter arising under a construction contract, the court or tribunal—
(a) must allow for any amount paid to a party to the contract under or for part 3 in any order or award it makes in those proceedings; and
(b) may make the orders it considers appropriate for the restitution of any amount so paid, and any other orders it considers appropriate, having regard to its decision in the proceedings.”
[16] It follows that while an adjudication decision gives rise to a right to payment in favour of a contractor, the decision does not preclude recovery of (or obtaining credit for) the amount the subject of the adjudication decision in subsequent civil proceedings. For that reason, an adjudication decision may be described as an interim decision, or a decision made on an interim basis.
Availability of relief
[17] MKG submits that declaratory relief is not available to QBWSA, subsequent to the registration of the adjudication certificate as a judgment. It submits that to grant a declaration while the judgment stands would be an impermissible collateral attack on the judgment; and that if the judgment were set aside, then it would be inappropriate also to grant declaratory relief. It is not necessary to determine this issue unless QBWSA succeeds in establishing that the decision is void.
[18] MKG has, in this context, referred to s 31(4) of the Payments Act . That subsection envisages proceedings to set aside the judgment resulting from the registration of the certificate. However, it provides that where such proceedings have been commenced, the party commencing them may not challenge the adjudicator’s decision. Mr Bond SC who appeared with Mr Ambrose of Counsel for MKG expressly adopted the position that the judgment might be set aside if it were found that the adjudicator’s decision was void, notwithstanding this provision.
[19] Section 31(4)(b) requires QBWSA to pay into court the adjudicated amount, pending the final decision in the proceedings to have the judgment set aside. QBWSA has done this. Accordingly, if its submissions are made out, there is no reason not to set aside the judgment resulting from the registration of the adjudication certificate.
Broad test for good faith
[20] QBWSA attacks the adjudication on the ground that the adjudicator did not make a bona fide attempt to exercise the power conferred by the Payments Act . In support of its challenge, it relies upon a test for determining whether the adjudicator made a bona fide attempt to exercise his power, which the parties referred to as the broad test. MKG submitted that the authorities relied upon by QBWSA did not support the test as broadly as it was formulated on behalf of QBWSA , and in particular challenged the inclusion of a requirement that the adjudication be reasonable.
[21] MKG also contended that the correct test was significantly narrower than that formulated by QBWSA in any event. I shall discuss the test for which MKG contended later in these reasons.
[22] The reasoning which leads to the good faith requirement is based on the fact that the Payments Act , in conferring on an adjudicator the power to decide an adjudicated amount (and other matters), identifies matters which the adjudicator is required to consider. It follows that a decision cannot result in the consequences provided for by the Payments Act , unless it satisfies the requirements for such a decision, identified in the Payments Act .
[23] The question which results from that line of reasoning is, what consideration of the specified matters is necessary to satisfy the statutory conditions, producing a decision which has the consequences specified in the Payments Act (or alternatively, without which consideration, the decision will be held to be void). The question is strongly analogous to that considered by the High Court in Project Blue Sky Inc v Australian Broadcasting Authority . It is ultimately a question of the proper construction of the statute.
[24] Answers have been provided in other cases dealing with very similar legislation. In Brodyn Pty Ltd t/a Time Cost and Quality v Davenport, Hodgson JA (with whom the other members of the New South Wales Court of Appeal agreed) said the following (of provisions which included the New South Wales equivalent to s 26):
“A question arises whether any non-compliance with any of these requirements has the effect that a purported decision is void, that is, is not in truth an adjudicator's decision. That question has been approached in the first instance decision by asking whether an error by the adjudicator in determining whether any of these requirements is satisfied is a jurisdictional or non-jurisdictional error. I think that approach has tended to cast the net too widely; and I think it is preferable to ask whether a requirement being considered was intended by the legislature to be an essential pre-condition for the existence of an adjudicator's decision.
...
What was intended to be essential was compliance with the basic requirements (and those set out above may not be exhaustive), a bona fide attempt by the adjudicator to exercise the relevant power relating to the subject matter of the legislation and reasonably capable of reference to this power (cf. R v. Hickman; Ex Parte Fox and Clinton [1945] HCA 53 ; (1945) 70 CLR 598) and no substantial denial of the measure of natural justice that the Act requires to be given. ... (I)f a purported decision is not such a bona fide attempt ... then in my opinion a purported decision will be void and not merely voidable, because there will then not, in my opinion, be satisfaction of requirements that the legislature has indicated as essential to the existence of a decision.”
[25] The approach taken by Hodgson JA was adopted by Brereton J in Holmwood Holdings v Halkat Electrical Contractors . His Honour also said, in respect of an adjudicator’s decision:
“Accordingly, good faith as a condition of validity of the exercise of an adjudicator’s power to make a decision requires more than mere honesty. It requires faithfulness to the obligation. It requires a conscientious effort to perform the obligation.”
[26] To similar effect, in Timwin Construction Pty Ltd v Façade Innovation Pty Ltd , McDougall J, after referring to Brodyn , said:
“Clearly, I think, his Honour was not referring to dishonesty or its opposite. I think he was suggesting that, as is well understood in the administrative law context, there must be an effort to understand and deal with the issues in the discharge of the statutory function: see, for example, the speech of Lord Sumner in Roberts v Hopwood [1925] AC 578 , 603, (sic – 604) where his Lordship said that a requirement to act in good faith must mean that the board ‘are putting their minds to the comprehension and their wills to the discharge of their duty to the public, whose money and locality which (sic) they administer’.”
[27] However, QBWSA also contends that, to be valid, an adjudicator’s decision must be reasonable. In support of that contention it relies on Downer Construction (Australia) Pty Ltd v Energy Australia where Giles JA said:
“In my opinion, determination of the parameters of the payment claim is a matter for the adjudicator, and a reasonable but erroneous decision by the adjudicator does not invalidate the decision.”
[28] QBWSA also relies on the following passage from the decision at first instance in Holmwood Holdings :
“I have concluded, for the reasons which follow, that, in the present context, the broader view should apply, and in particular that recklessness or capriciousness on the part of the adjudicator in the performance of his or her function, such as to establish the absence of a genuine or conscientious attempt to perform the adjudicator’s function – short of a wilful and deliberate failure to attempt to perform the function – can amount to a want of good faith.”
[29] Some support is also drawn from the following passage from Timwin Construction :
“It is of course apparent that the adjudicator turned his mind to the submissions for Timwin. However, did he so (sic) in the context of dismissing them (on this issue) because of s 20(2B). Had he read, and given consideration to, the submissions for Façade, he could not reasonably have done this. That, to my mind, supports rather than denies the drawing of the inference that the adjudicator did not have regard to, or consider, the relevant submissions.”
[30] In challenging the inclusion of a requirement for reasonableness in the broad test for determining absence of good faith, Counsel for MKG point out that, in the appeal from the judgment of Brereton J in Holmwood Contractors , the Court of Appeal did not adopt the reasoning of Brereton J at first instance, and went on to point out that its silence on some matters should not be taken as approval of all that had been said at first instance. They further submit that the passage from Downer Construction which is relied upon does not attempt to state a test for review.
[31] It seems to me that those submissions are well-founded. In Downer Construction, in my respectful opinion, Giles JA was identifying a decision which was within the limits set by the statute, rather than seeking to identify those limits. In Halkat Electrical Contractors v Holmwood Holdings Pty Ltd , which was the appeal from the decision at first instance in Holmwood Contractors the Court of Appeal plainly treated with caution parts of the reasons for judgment at first instance. In Timwin Construction , McDougall J, it seems to me, was identifying a factual matter which, in the context of that case, helped his Honour to reach a conclusion about whether the adjudicator had in fact considered a particular submission.
[32] It may be correct to say that a decision which displays an extreme degree of unreasonableness akin to that described in Associated Provincial Picture House Ltd v Wednesbury Corporation , is not a decision for the purposes of s 26 of the Payments Act . Otherwise, I do not consider an adjudicator’s decision purporting to be made under the Payments Act will be invalid if it is not “reasonable”. The Payments Act seeks to provide a mechanism for obtaining a decision which will be quick, but in a sense, provisional. It does not seem to me, consistent with the general object and tenor of the Act, to impose a requirement of “reasonableness”.
[33] I am therefore of the opinion that the test advanced on behalf of QBWSA is too widely formulated. If the broad test for good faith is to be adopted, then what is required is a genuine attempt to exercise the power in accordance with the provisions in the Payments Act . Specifically, in relation to a consideration of the construction contract, what is required is a genuine attempt to understand and apply that contract.
QBWSA ’s submissions on adjudicator’s use of the Facsimile
[34] QBWSA submits that the adjudicator’s reliance on the Facsimile led him into jurisdictional error. It submits that the adjudicator found that, as a result of the Facsimile, the Superintendent had invited MKG to tender on the basis that any quantity of hard rock encountered in the project would be treated as a latent condition under the contract, thereby reversing the allocation of risk under the contract and overriding provisions of the contract, with the result that the adjudicator did not pay proper regard to clause 12. It submits that the adjudicator’s interpretation of the Facsimile enabled him to compensate MKG , not in accordance with the contract, but ultimately in line with the non-conforming tender. It was an invitation to lodge a tender on the basis that any rock to be excavated in the course of the project which could not be precisely quantified on the basis of the geotechnical report, would be treated as a latent condition under the contract. He accordingly treated the Facsimile as “a contractual document”. The result, it was submitted, was that the adjudication was not based on a bona fide consideration of the contract. In support of these propositions, QBWSA pointed to a number of paragraphs from the adjudication decision.
[35] In the preceding paragraph, I have tried to assemble the principal propositions advanced on behalf of QBWSA , relating to the adjudicator’s use of the Facsimile. It supports these propositions by two related submissions.
[36] The first is that, in fact, the adjudicator set about ensuring that MKG was fairly compensated. Again, QBWSA relies upon a number of passages in the adjudicator’s decision. The second related submission is that in truth, the adjudicator sought to give effect to the non-conforming tender; or he took it into account when it was not a relevant consideration under the Payments Act . Again, these submissions are supported by reference to specific paragraphs of the adjudicator’s decision.
[37] QBWSA also draws some support for its position from the fact that the adjudicator took the view that clause 14 of the Job Specification, and the Facsimile, and the geotechnical report may have been misleading. In doing so, passages from the adjudicator’s decision were again relied upon. This submission seems to lead to a suggestion that the adjudicator had a disposition to find for MKG on a basis other than the provisions of the contract, and accordingly not to carry out his duty under s 26 of the Payments Act .
[38] These submissions make it necessary to consider the adjudicator’s decision in some detail.
Adjudication decision
[39] The adjudication decision was delivered on 20 June 2008, 18 days after MKG’s adjudication application, and 9 days after QBWSA ’s adjudication response. That reflects the time limitations imposed on the adjudicator by s 25(3) of the Payments Act.
[40] The principal issue dealt with in the adjudicator’s decision was the latent condition claim. Central to its determination was clause 12.1 of the General Conditions of Contract (AS 2124-1992), which formed part of the construction contract. It was in the following terms:
12.1 Definition
Latent Conditions are-
(a) physical conditions on the Site or its surroundings, including artificial things but excluding weather conditions, which differ materially from the physical conditions which should reasonably have been anticipated by the Contractor at the time of the Contractor’s tender if the Contractor had-
(i) examined all information made available in writing by the Principal to the Contractor for the purpose of tendering; and
(ii) examined all information relevant to the risks, contingencies and other circumstances having an effect on the tender and obtainable by the making of reasonable enquiries; and
(iii) inspected the Site and its surroundings; and
(b) any other conditions which the Contract specifies to be Latent Conditions.
[41] After the discussion of some other preliminary matters, the adjudicator considered the contract and the original tender of 11 April 2006. In doing so, he considered the Bill of Quantities, which became part of the contract. He noted an apparent anomaly in that a number of items of work appear to have been set out twice in the Bill of Quantities. It was in respect of one of the entries for excavation in rock (item 11) that the provisional amount was included in the original tender. The adjudicator then characterised this tender as a tender for a lump sum amount of $11,962,292 (excluding rock excavation); and in view of the amount of excavation relied upon by MKG in its claim before him, a claim for rock excavation of $10,046,000. He then commented that that result was comparable with other tenders; and observed that the latent condition claim which he had to determine was a claim for an amount equivalent to that which would have been payable under the original tender.
[42] The adjudicator then went on to consider the letter from MKG of 21 April 2006. He referred to this document as the second tender, although in truth it provided some additional information, and modified the original tender in respect of item 11. I shall refer to it as the modified tender. In the course of doing so, the adjudicator referred to some matters raised by the adjudication response (from QBWSA ). This is a document which, it seems to me, the adjudicator was required to take into account under ss 24 and 25 of the Payments Act . The first of those matters was the relativity of the modified tender to other tenders - with the exception of a tender made in error which was withdrawn, the tender by MKG was by comparison with the other tenders very low. The second was the reliance by QBWSA on the original tender as showing a recognition of significant risks relating to the excavation of rock. It is in that context that the adjudicator expressed the view that MKG’s likely contract price was much greater then the stated figure of $13,158,521, the basis for that observation being that it covered only a limited quantity of excavation of rock.
[43] In dealing with QBWSA ’s submission about the recognition of risks associated with the excavation of rock, the adjudicator discussed the geotechnical report. That document had been available to MKG at the time of its original tender. It is in the context of that discussion that the adjudicator noted that inferences, which the adjudicator considered most material, had been drawn by Mr Morley, who supervised the excavation work for the geotechnical report; and that these inferences were not disclosed in that report. He then observed that the representation made in clause 14 of the Job Scope (another contract document) that the geotechnical report represented the inference drawn by “the operator” from drilling and test pit excavation operations may be misleading and deceptive. However, he noted that he was not called upon to decide a claim under the Trade Practices Act 1974 (Cth).
[44] He then expressed the view that QBWSA (or its consultant, the Superintendent) appreciated the significant risk of encountering rock, and noted that (subsequent to the geotechnical report) the Superintendent had written to QBWSA stating that adequate information had been provided to allow excavation to be priced as a lump sum. Against that background, the adjudicator characterised the Facsimile as a request of QBWSA to make a new offer based upon its assessment, from the information available, of a price for rock excavation. He considered this to be inconsistent with the geotechnical report itself, which stated it was not possible to identify areas where rock might be particularly difficult to excavate, as a result of which the adjudicator considered the information to be patently inadequate to price rock excavation. He then returned to a consideration of the adjudication response from QBWSA, where it was asserted that it was for MKG to assess and price the risks of rock excavation. It was in dealing with that submission that the adjudicator expressed the view that the risk of latent conditions remained with QBWSA ; and that QBWSA appeared to have misconstrued the risk allocation made by the contract.
[45] The adjudicator then identified the Facsimile as a factor relevant in deciding what should have been anticipated by an experienced and competent contractor, an obvious reference to the test for the existence of latent conditions under clause 12.1.
[46] The adjudicator further considered a submission made in QBWSA ’s adjudication response that MKG had in fact anticipated that rock excavation would be required, but considered that this could be the subject of a claim based on a latent condition. In commenting on that matter, the adjudicator considered MKG’s position as confirmation that the quantity of hard rock anticipated by MKG at the time of tendering was vastly less than the quantity actually encountered.
[47] The adjudicator then went on to characterise the latent condition on which MKG was relying in the adjudication as being the quantity of hard rock, rather then simply its existence in the area where the excavation had to be carried out. He then considered, in the context of the case presented on behalf of QBWSA in the adjudication, whether the quantity of rock should reasonably have been anticipated at the time of tendering.
[48] The adjudicator then proceeded to consider the geotechnical report, and its significance in light of QBWSA ’s adjudication response. It seems to me that the adjudicator, in carrying out this exercise, kept in mind the test for latent conditions found in clause 12.1 of the construction contract, as well as the submissions made by QBWSA in its adjudication response.
[49] One of QBWSA ’s submissions was that MKG’s estimate of the quantity of hard rock was completely flawed. In that context, the adjudicator expressed the view that that may have been the result of unconscionable conduct by the Superintendent or QBWSA , but thought it more likely that the contract had been misconstrued.
[50] The adjudicator then gave specific consideration to clause 12.1. He noted that MKG contended that site conditions were materially and substantially different to those which it anticipated, and expressed the view that MKG was an experienced and competent contractor. However, he also noted that the test in clause 12.1 was formulated by reference to what he referred to as “a notional experienced and competent contractor”, which he also noted to be different from the test advanced in QBWSA ’s adjudication response.
[51] The adjudicator then considered a report relied upon by QBWSA from Golder Associates, but did not accept its conclusions because, in his view, the report did not deal with the test formulated in clause 12.1. In dealing with the Golder Report the adjudicator again made reference to the statement in the Facsimile to the effect that adequate information had been provided to enable excavation to be priced as a lump sum. In that context, the adjudicator expressed the view that the author of the Facsimile was either misrepresenting the true position; or the author was asking MKG to price, as a lump sum, only such rock excavation as could be quantified from the information which had been provided to it, thereby accepting that any additional excavation would be a latent condition.
[52] The adjudicator then considered the evidence of Mr Morley. In doing so, he made reference to the test formulated in clause 12.1 for the existence of latent conditions. He also noted that Mr Morley, who had supervised the site testing, had information about what was observed, which was not included in the geotechnical report.
[53] He then considered the evidence from Mr Betts who had been a project engineer with the Superintendent. The adjudicator was, at least by inference, critical of the Superintendent’s conduct in dealing with MKG during the tendering process. However, he accepted a submission made on behalf of QBWSA that it would be highly inappropriate for him to make a finding of dishonesty in relation to the conduct of any person representing the Superintendent.
[54] He then concluded that MKG had satisfied him that it had encountered the latent condition claimed.
Absence of good faith and the Facsimile
[55] In my view, to determine whether or not the adjudicator has genuinely attempted to understand and apply clause 12.1, it is necessary to consider as a whole those parts of the adjudication decision where the adjudicator determined whether MKG’s basis for its claim for compensation for encountering a latent condition had been established. In particular, it is necessary to consider those parts of the adjudication decision on which QBWSA principally relies for its submission of absence of good faith, in the context in which they occur.
[56] It seems to me that the adjudicator was clearly very conscious of the provisions of clause 12.1 in considering this question. He reproduced the clause in the adjudication decision. He made repeated references, though often in a summary way, to the test formulated in it. In my view, a reading of those parts of the adjudication decision which deal with the question whether MKG had established the existence of a latent condition clearly reveals that the adjudicator was very conscious of the provisions of clause 12.1, and reached his conclusion by reference to the provisions of that clause, as he understood it.
[57] The criticisms based on particular passages in the adjudication decision fail, in my opinion, to take sufficient account of the context in which those passages occur. Generally, they form part of a response to specific submissions made by QBWSA in its adjudication response, or form part of an evaluation of evidence of individual witnesses. They do not seem to me to form the basis of the adjudicator’s application of clause 12.1. Indeed, in my view it would be extremely difficult to conclude that they did, when the adjudicator has on occasion expressly recognised that some of the matters on which he expressed a view were not relevant to a conclusion whether a latent condition existed by reference to clause 12. These statements in the adjudication decision are particularly significant in light of the fact that QBWSA does not assert actual dishonesty on the part of the adjudicator, or the presence of bad faith. The fact that it does not make these assertions is, in my view, appropriate, in view of the adjudicator’s reasons, read as a whole.
[58] QBWSA places great weight on the use made by the adjudicator of the Facsimile in finding for MKG in the adjudication. In a number of places, the adjudicator has referred to the Facsimile as a matter relevant for the application of the test for the existence of a latent condition stated in clause 12.1.
[59] Elsewhere, the adjudicator referred to the Facsimile in dealing with a submission in QBWSA ’s adjudication response referring to the fact that in the Facsimile, QBWSA required a tender which provided for a lump sum priced for the project. On analysis, it appears to me that the question which the adjudicator was considering at this point of the adjudication decision was whether the extent of hard rock to be excavated was a latent condition, having regard to the test formulated in clause 12.1. The same may be said of the reference to the Facsimile in the course of the discussion of the geotechnical report.
[60] QBWSA submits that the adjudicator used the Facsimile to identify a contract under which the contract amount represented a lump sum for only a small part of the excavation which the project called for, and which accordingly was a contract different from the construction contract made between the parties. It submits that accordingly the adjudication decision was beyond power, because the adjudicator was limited by s 26(2) of the Payments Act to a consideration of the construction contract. This submission is related to a submission which I shall deal with later in these reasons.
[61] I consider that the adjudicator has made a bona fide attempt to understand and to apply clause 12.1; and that he has not failed to give consideration to the construction contract. I therefore do not accept QBWSA ’s submissions that the adjudication decision is void, because of an absence of good faith on the part of the adjudicator, in giving consideration to the construction contract.
MKG’s test for good faith
[62] Counsel for MKG submit that the applicable test for determining the validity of the adjudicator’s decision on the ground that the adjudicator has failed to carry out in good faith an action required by the Payments Act , is that found in a series of decisions of the Federal Court, both at appellate level and at first instance.
[63] In these cases, the test is usually, though not always, formulated with reference to bad faith.
[64] Under this test, the inquiry is directed to the actual state of mind of the decision maker. For the ground to be made out, the court must find that the decision maker “was recreant to his duty by wilfully and deliberately making the impugned decision without attempting to carry out the statutory duty lying upon him - tossing a coin without reading the file, allowing in every third applicant (for review of a refusal to grant a visa), or allowing in applicants from various countries in rotation might be examples”.
[65] Recklessness in the exercise of the power may not be sufficient to establish bad faith, unless it amounts to actual wrongful intent. It is doubtful that capriciousness alone will demonstrate bad faith, unless whim or fancy has consciously been preferred to considered judgment.
[66] While actual bias may be a manifestation of bad faith, that will not be the case where actual bias occurs subconsciously, presumably because bad faith requires a conscious intent to do something which is wrong.
[67] It follows that an allegation of bad faith is a serious matter, involving personal fault on the part of the decision maker. A decision by an advocate to make an allegation of bad faith gives rise to a question of professional ethics: like an allegation of fraud, an allegation of bad faith should not be made unless there are proper grounds for doing so.
[68] It is a large step to jump from a decision involving errors of fact and law, to a finding that the decision maker acted in bad faith. Not surprisingly, bad faith in this sense is very rarely established.
[69] It will be apparent that the description of this ground, and the consequences which are said to follow from that description, are quite different from the ground as contended for by Counsel for QBWSA , or the modified version of their test to which I have referred previously.
[70] Some of the cases propounding the strict view of bad faith draw upon the grounds formulated in the Administrative Decisions (Judicial Reviews) Act 1977 (Cth), where bad faith is a separate ground from, for example, improper exercise of a power conferred by the statute, More generally, the cases relied upon by MKG are cases where review is sought of decisions made under the Migration Act 1958 (Cth), which includes s 474. That section provides that a decision to which it applies is final and conclusive; must not be challenged, appealed against, reviewed, quashed or called into question in any court; and is not subject to prohibition, mandamus, injunction, declaration, or certiorari. The presence of such a clause makes it necessary to determine whether a decision purportedly made under the Migration Act is a decision which qualifies for the protection conferred by the section. The result will be the outcome of a construction of the Migration Act as a whole, including the provisions which identify requirements for the exercise of the decision-making power and a privative provision such as s 474. There is no general rule as to the meaning or effect of privative clauses such as s 474 ; and the outcome of the process of construction to which I have referred will depend entirely on the statutory provisions under consideration.
[71] I note that, notwithstanding the passages in the cases referred to by Counsel for MKG , the expressions “absence of good faith” and “bad faith” do not always carry the pejorative connotations and significant consequences which I have attempted to summarise earlier in these reasons. For example, Wade and Forsyth write:
“It is extremely rare for public authorities to be found guilty of intentional dishonesty: normally they are found to have erred, if at all, by ignorance or misunderstanding. Yet the courts constantly accuse them of bad faith merely because they have acted unreasonably or on improper grounds. Again and again it is laid down that powers must be exercised reasonably and in good faith. But in this context ‘in good faith’ means merely ‘for legitimate reasons.’ Contrary to the natural sense of the words, they impute no moral obliquity.”
[72] The authors also refer to cases where the expression “in good faith” has a meaning similar to that contended for by Counsel for QBWSA , and the expression “ mala fide ” means to act for a purpose not authorised by the statute conferring the power.
[73] Although a statutory order for review of an adjudicator’s decision under the Payments Act can no longer be sought under the Judicial Review Act 1991 (Qld), nevertheless the Payments Act does not itself include any provision which makes an adjudicator’s decision final, or which precludes a declaration about its validity. On the contrary, as noted, an adjudicator’s decision has an interim quality. It is obvious, therefore, that the question of the minimum requirements for the validity of an adjudicator’s decision is to be determined in a statutory context quite different to the Migration Act .
[74] On the other hand, the cases relied upon by Counsel for QBWSA deal with legislation that is very similar to the Payments Act , and include decisions from the New South Wales Court of Appeal.
[75] If it were necessary for me to do so, I would follow the approach taken in the decisions relied upon by Counsel for QBWSA in preference to that relied upon by Counsel for MKG . On either approach, in my view, the adjudicator’s decision should not be found to be void on the ground that he has not acted in good faith.
Absence of evidence of quantum of claim
[76] QBWSA submits that the adjudicator’s decision is invalid because he determined the amount of the payment, without any proper evidence upon which the decision could be made.
[77] Counsel for QBWSA submit that MKG’s claim had to be supported by evidence of the amount due. They rely in part on the decision of the New South Wales Supreme Court in Brewarrina Shire Council v Beckhaus Civil Pty Ltd . That case held that under clause 42.1 of AS214/1992 the provision of evidence of the amount due in support of a claim was a condition precedent to the obligation arising from the contract for the superintendent to issue a payment certificate. This conclusion resulted from the construction of the contract. No issue arose of the validity of a decision made under legislation similar to the Payments Act .
[78] Reliance was also placed on the decision of the New South Wales Court of Appeal in Halkat Electrical Contractors Pty Ltd , where the adjudicator had adopted the figure advanced by one of the parties, without any evidence which would have enabled him to arrive at the value of the work. The decision was held to be void, because he arrived at an adjudicated amount by a process wholly unrelated to a consideration of the matters specified in the New South Wales equivalent of s 26(2).
[79] On the basis of these decisions, Counsel for QBWSA submit that the onus lay on MKG to prove the quantities of rock which were the subject of its claim.
[80] Counsel for QBWSA support their submission by reference to the fact that there was a very great discrepancy between the total of the amounts which were the subject of previous claims, and the amount the subject of the claim before the adjudicator, which was intended to replace them.
[81] The adjudicator recorded that he had statutory declarations from Mr Latimer and Mr Keen of MKG , establishing that MKG had to carry out additional work, use additional construction plants, and incur extra cost, in dealing with rock. He then expressed the view that it was necessary for MKG to demonstrate the quantities of rock excavated, though not the costs actually incurred. It was not necessary to prove costs, in the adjudicator’s view, because of the agreed rate.
[82] The adjudicator then noted that he had an estimate of the quantity of rock which had been excavated by MKG . Of this, he said that for the purpose of the progress payment, he saw no problem with estimates. The comment would appear to be based upon the interim nature of such a payment. The adjudicator subsequently accepted that the estimate was a reasonable estimate, and noted that QBWSA had not provided any evidence of the quantity of rock excavated.
[83] The adjudicator’s approach was criticised, because the estimate was based upon the geotechnical report, which the adjudicator had earlier stated did not provide adequate information upon which to price rock excavation. However, it is to be noted that there is a significant difference between the position of a contractor who was in possession of the geotechnical report at the time of tendering, and the position of the adjudicator. The adjudicator was carrying out his task after the work had been done, and extensive rock had been encountered. Moreover, the adjudicator, unlike a contractor at the time of tender, had evidence from Mr Morley, who supervised the geotechnical investigation, that the test pit results showed where hard rock was encountered, and provided a reasonable basis for the assessment of the quantity of rock excavated. The adjudicator also recognised, and recorded, that there was a significant difference between the total of the previous claims, and the amount claimed in the adjudication – he noted that it was an eight fold increase in the amount claimed.
[84] Unlike Halkat Electrical Contractors, this is not a case where there was no evidence whatever upon which the amount of the claim could be determined. Whether or not a court would come to the conclusion reached by the adjudicator is beside the point. The question is whether he has made a determination under s 26 of the Payments Act , or whether he arrived at the amount he has adopted by a process wholly unrelated to a consideration of the matters set out in s 26(2). It has not been suggested that the evidence to which he has referred, including the estimate, was outside the range of considerations identified in s 26(2).
[85] I am therefore of the view that QBWSA has failed to establish that the adjudication decision is void on the basis that there was no evidence on which the adjudicator could determine the amount of the claim.
Other Matters
[86] A number of other grounds are relied upon on behalf of QBWSA . They include the following:
(a) The adjudicator arrived at his decision by having regard to matters other than those specified by the Payments Act , and in so doing, failed to have proper regard to the contract;
(b) The adjudicator found for MKG on a basis not the subject of either party’s submissions, and without providing an opportunity to QBWSA to provide submissions on the issue;
(c) The adjudicator made no mention of and did not apply a leading and relevant authority, addressed by each party in its submissions, regarding a contractor’s entitlement to recover for late conditions.
[87] There are other matters raised in the submissions made on behalf of QBWSA which seem to me to be either supportive of the submissions which I have attempted to summarise, or else responsive to submissions of MKG , and which I do not consider it necessary to deal with specifically to determine the outcome of this application.
[88] The first two grounds may be considered together. In essence, the bases for these grounds are the following:
(a) The adjudicator had regard to the tender lodged in 11 April 2006;
(b) The adjudicator was concerned to provide what he considered to be “fair compensation” to MKG ;
(c) The adjudicator had regard to his view of the amount which MKG would have recovered, had its first tender been accepted unchanged;
(d) The adjudicator took into account the Facsimile as a contractual document;
(e) The adjudicator failed to have regard to the plain words of clause 12.1(a) of the contract, thereby failing to apply the contract;
(f) The adjudicator formed the view that the conduct of those associated with QBWSA was misleading conduct or potentially otherwise actionable.
[89] The submissions relating to error about the construction contract were extended to a submission that the adjudicator assessed the payment claim under the wrong contract.
[90] Earlier in these reasons, I have set out my view of the way that the adjudicator carried out his task. In doing so, I have dealt with a number of matters relevant to the determination of these two grounds. In my opinion, the adjudicator undertook the task he was required to perform under the Act, and reached his conclusions having regard to the matters he was required to have regard to under the Payments Act. To the extent that he took into account other matters, it seems to me that he did so for the purpose of understanding, or applying, the construction contract. In particular, I do not consider he regarded the Facsimile as a document that formed part of the contract. Rather, he used it to apply the test which is formulated in clause 12.1.
[91] For similar reasons, I do not think that the adjudicator erred in determining the claim under a contract other than the construction contract. I should add that I do not consider that some error in relation to the terms of the construction contract would invalidate the adjudicator’s decisions.
[92] Counsel for QBWSA have referred to authorities which show that an error of law in interpretation of the contract does not invalidate an adjudicator’s decision. Thus in Plaza West Pty Ltd v Simon’s Earthworks (NSW) Pty Ltd , Hammerschlag J said:
“An error of law or fact including an error in interpretation of the Act or contract as to what are the valid and operative terms of the contract does not prevent a decision from being an adjudicator’s decision within the meaning of the Act. Section 22 (2) of the Act (the New South Wales equivalent of s 26 of the Payments Act ) requires the adjudicator to consider the provisions of the contract and the provisions of the Act but so long as the adjudicator does this or at least bona fide addresses the requirements of s 22 (2) as to what is to be considered an error on these matters does not render the decision invalid.” ( Emphasis added )
[93] His Honour’s reasoning was upheld on appeal to the Court of Appeal. That court cited its earlier decision, Minister for Commerce v Contrax Plumbing (NSW) Pty Ltd , where Hodgson JA (with whom the other members of the Court agreed on this point) said:
“In my opinion, an error of fact or law, including an error in interpretation of the Act or the contract, or as to what are the valid and operative terms of the contract , does not prevent a decision from being an adjudicator’s decision within the meaning of the Act.” ( Emphasis added)
[94] In Brodyn , Hodgson JA (with whom the other members of the Court agreed) pointed out that the matters raised by the New South Wales equivalent of s 26(2) could involve extremely doubtful questions of fact or law, for example, whether a particular provision such as a variation is or is not a provision of the construction contract, and continued:
“In my opinion it is sufficient to avoid invalidity if an adjudicator either does consider only the matters referred to in s 22(2), or bona fide addresses the requirements of s 22(2) as to what is to be considered.”
[95] This approach can be traced back to the decision of McDougall J in Musico v Davenport where his Honour drew an analogy between an adjudicator and a person to whom parties have submitted a dispute for expert decision, and concluded that where the decision of a dispute under the New South Wales equivalent of the Payments Act requires the adjudicator to consider issues of law, the adjudicator will not fall into jurisdictional error simply because he or she makes an error of law in the consideration and decision of those issues. That view was adopted by the New South Wales Court of Appeal in Brodyn .
[96] The alternative view is that s 26(2) of the Payments Act requires the adjudicator to consider the construction contract, and if he or she makes a mistake in correctly identifying the contract, that mistake will invalidate the decision.
[97] I consider the approach taken in the New South Wales decisions to be more likely to reflect the presumed intention of the legislature when adopting the Payments Act . Further, there are now a significant number of judgments in New South Wales which have come to a consistent conclusion, including decisions of the New South Wales Court of Appeal. Accordingly, I would adopt the approach taken in those cases.
[98] Because I do not accept that the adjudicator decided the payment claim on the basis which QBWSA submits, I also do not accept its submission that the adjudicator substantially breached the requirements of natural justice by failing to give it notice of his intended approach. I note that MKG makes a submission that a breach of the rules of natural justice would not invalidate the adjudicator’s decision, but it is unnecessary to rule on this submission.
[99] The third ground is based on the fact that the adjudicator did not refer to the decision in BMD Major Projects Pty Ltd v Victorian Urban Development Authority. That case discusses the application of clause 12.1, and the extent to which a contractor should make inquiries about site conditions. QBWSA submits that the fact that BMD Major Projects is not referred to in the adjudication decision can only be explained by a failure by the adjudicator to pay any regard to it, and that accordingly, his determination is void.
[100] As I have previously indicated, I consider that the adjudicator formed a view about the correct application of clause 12.1, and applied that view. The fact that in doing so, he has not mentioned BMD Major Projects in the adjudication determination does not, in my view establish that he has failed to consider the case. I have previously noted the very short time within which an adjudicator is required to make his determination. The adjudication response from QBWSA dated 11 June 2008 was 1,248 pages in length. The submission within it occupied 54 pages, and was supported by three expert reports and seven witness statements. Given the compressed timeframe, and the need to consider MKG’s adjudication application (some 1,303 pages in length) as well as the payment claim and payment schedule, it would be surprising if every matter considered by the adjudicator was recorded in the adjudication decision.
[101] Counsel for MKG submit that even if it were established that the adjudicator failed to consider BMD Major Projects , that would not invalidate his decision. They rely on the following passage from the judgment of Hodgson JA (with whom Beazley JA agreed) in John Holland Pty Ltd v Roads and Traffic Authority of New South Wales :
“The relevant requirement (of s 26(2)) is that the adjudicator consider the provisions of the Act, the provisions of the contract and submissions duly made. If an adjudicator does consider the provisions of the Act and the contract which he or she believes to be relevant, and considers those of the submissions that he or she believes to have been duly made, I do not think an accidental or erroneous omission to consider a particular provision of the Act or a particular provision of the contract, or a particular submission, could either wholly invalidate a determination or invalidate it as regards any part affected by the omission.”
[102] It is apparent from the adjudication decision that substantial consideration has been given to the submission made by QBWSA in the adjudication. Even if there were a failure to consider one matter raised in the submission, it does not seem to me that that would invalidate the adjudicator’s decision.
[103] I therefore do not consider that the adjudication decision has been established to be void on this ground.
[104] No other basis has been advanced for setting aside the judgment obtained by MKG against QBWSA . Accordingly, the application to set aside that judgment will be dismissed.
Stay of execution
[105] As I have mentioned, QBWSA has also sought a stay of execution of the judgment entered on behalf of MKG under s 31 of the Payments Act.
[106] There has been no suggestion that there is no power to grant the stay. Under r 800 of the UCPR , enforcement of a money order may be stayed. It has been recognised in New South Wales, that a judgment which is the result of the filing of an adjudication certificate may be stayed. There is no reason to doubt the existence of power in Queensland to stay the enforcement of a judgment entered under s 31 of the Payments Act .
[107] In Grosvenor Constructions , Einstein J considered that the policy of the Act, which is that successful claimants be paid, was a factor that should be taken into account in deciding whether to grant a stay. However, he also considered that where there is certainty that a party’s right to challenge the outcome recorded in the certificate would otherwise be rendered nugatory, and that that party would suffer irreparable prejudice, the proper and principled exercise of the discretion would be to grant a stay. In that case, those consequences followed from the fact that the party who had the benefit of the judgment was insolvent.
[108] As previously mentioned, MKG has been placed in liquidation. It accepts that this provides support for the application for a stay.
[109] However, it submits that the stay should be subject to conditions that QBWSA undertake to commence proceedings pursuant to s 100 of the Payments Act within a nominated period of time, and to pursue those proceedings diligently; and that QBWSA pay the adjudicated amount into Court as security pending the final determination of those proceedings, with MKG having leave to withdraw part of the amount paid into court for the purpose of conducting the s 100 proceedings.
[110] Consistently with these submissions, I was told that in respect of the stay, the only issues were the nature (which I understood to refer to the terms) of a condition relating to the prosecution of proceedings under s 100; and whether MKG should have access to moneys in court before a resolution of those proceedings.
[111] The contentious issue is whether MKG should have access to the money in court for the purpose of funding its defence to proceedings instituted to QBWSA under s 100 of the Payments Act .
[112] The principal argument advanced on behalf of MKG is that the policy of the Act is to enable a party who has the benefit of an adjudication determination to have the funds the subject of the adjudication, pending a final determination as envisaged by s 100 of the Payments Act . However, it is acknowledged by MKG that the Payments Act envisages a final determination which may be adverse to it, and accordingly that it may be required to refund money paid to it consequent upon the adjudication determination. QBWSA’s right to recover such money would be defeated if MKG were permitted to fund litigation envisaged by s 100 of the Payments Act , from funds paid into court by QBWSA .
[113] MKG also says the policy of the Act is that it not be exposed to any financial risk concerning the financial position of QBWSA . If that is correct, any concern about the financial position of QBWSA is removed by the payment into Court.
[114] QBWSA also submits that the evidence discloses that the current secured creditor has paid out a previous secured creditor, and that there was no evidence that the receivers or the liquidators are unable to fund litigation envisaged by s 100 of the Payments Act . It was not submitted on behalf of MKG that unless the condition were imposed, it would not be in a position to contest those proceedings.
[115] In those circumstances, I do not intend to impose a condition permitting MKG to have access to the funds paid into court by QBWSA , for the purposes of contesting such proceedings.
[116] I do, however, intend to impose a condition on the stay which would require QBWSA to commence proceedings to determine that MKG is not entitled to the amount identified by the adjudication determination, within 28 days; and that it undertake to prosecute such proceedings diligently.
Costs
[117] The major matter which was litigated in these proceedings was the validity of the adjudication determination. On that matter, QBWSA was unsuccessful. The only other matter in contest was the condition which MKG sought to have imposed on the order staying enforcement of the judgment. Although MKG was unsuccessful on this matter, it was a very minor part of the dispute. QBWSA points out that it has had costs associated with the application for the stay, even if it was ultimately not opposed. However, before it filed its application on 22 September 2008, MKG’s solicitors undertook not to take any step to enforce the judgment without first giving QBWSA 28 days written notice of its intention to do so. There is no suggestion MKG gave notice that it was taking steps to enforce the judgment. In those circumstances, I propose to order that QBWSA pay MKG its costs of the application.
Conclusion
[118] The application by QBWSA for a declaration that the adjudication determination dated 20 June 2008 is void, will be dismissed, as will the application to set aside the judgment entered by MKG consequent upon the adjudication determination. I intend to order that enforcement of the judgment be stayed until further order, on condition that QBWSA commence proceedings against MKG to determine that it is not liable to MKG for the amount stated in the adjudication decision, within 28 days; and on the further condition that it undertake to prosecute those proceedings diligently. QBWSA will be ordered to pay MKG’s costs of and incidental to this application, to be assessed on the standard basis.