JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL

 

STREAM : COMMERCIAL & CIVIL

 

ACT : CONSTRUCTION CONTRACTS ACT 2004 (WA)

 

CITATION : LONGMONT CONSOLIDATED PTY LTD and FLEETWOOD PTY LTD [2010] WASAT 23

 

MEMBER : MR C RAYMOND (SENIOR MEMBER)

MS J HAWKINS (MEMBER)

 

HEARD : 18 NOVEMBER 2009

 

DELIVERED : 17 FEBRUARY 2010

 

FILE NO/S : CC 1447 of 2009

 

BETWEEN : LONGMONT CONSOLIDATED PTY LTD

Applicant

AND

FLEETWOOD PTY LTD

Respondent

 

Catchwords:

Construction Contracts Act 2004 (WA) - Application for review of decision by adjudicator to dismiss - Grounds of dismissal that application not served in time - Whether provisions of Sch 1, Div 5 to be implied

 

Legislation:

Construction Contracts Act 2004 (WA), s 3, s 6, s 16, s 17, s 18, s 26, s 26(1), s 46(1), s 53, Sch 1 Div 5, Sch 1 Div 5 cl 7, Sch 1 Div 5 cl 7(3)

 

Result:

Application for review dismissed

 

Category: B

 

Representation:

 

Counsel:

Applicant : Mr G Morrow

Respondent : Mr CA Ryder

 

Solicitors:

Applicant : Downings Legal

Respondent : Corrs Chambers Westgarth

 

Case(s) referred to in decision(s):

Longmont Consolidated Pty Ltd and Fleetwood Pty Ltd [2010] WASAT 22

 

REASONS FOR DECISION OF THE TRIBUNAL :

 

Summary of Tribunal's decision

 

1 The applicant applied under s 46(1) of the Construction Contracts Act 2004 (WA) to review a decision of an adjudicator to dismiss an adjudication application as being out of time without a determination of the merits.

 

2 The Tribunal held that the decision of the adjudicator to the effect that the adjudication application was out of time was correct, although for different reasons.

 

3 The Tribunal concluded that the relevant contractual provision concerning payments to the applicant was dependent on an approved invoice being submitted. The relevant contractual provision required the applicant to submit estimates of work performed and projected for performance during that month and by the 20th of each month. Once such an estimate is provided, the respondent was required to review the estimates and, upon approval, return them to the applicant to be submitted on the 1st of the following month. The relevant clause went on to provide that only following that process was the respondent to make payment to the applicant 30 days after receipt of an approved invoice.

 

4 The Tribunal held that the relevant contractual provision was silent as to what was to occur should an estimate not be approved or where no response to an estimate was given, and therefore did not provide a mechanism for making or responding to a payment claim, as defined in s 3 of the Construction Contracts Act 2004 (WA).

 

5 Alternatively, the Tribunal found that such a contractual provision purports to modify or restrict the operations of the Construction Contracts Act 2004 (WA) and had no effect by virtue of s 53 of that Act.

 

6 On either bases, the Tribunal found that s 16, s 17 and s 18 of the Construction Contracts Act 2004 (WA) applied and that, consequently, no payment dispute ever arose and, therefore, the adjudication application was made within 28 days of a payment dispute arising.

 

7 The Tribunal, therefore, dismissed the application to review.

 

Decision under review

 

8 This is an application for review under s 46(1) of the Construction Contracts Act 2004 (WA) (CC Act) of an adjudication decision. The adjudication decision related to spotters costs and is dated 24 August 2009, being adjudication No 04-09-12 (Spotters Costs decision). This matter was heard together with another application for review made by the applicant, being CC 1442/2009. The review in CC 1442/2009 ( Longmont Consolidated Pty Ltd and Fleetwood Pty Ltd [2010] WASAT 22) concerned an adjudication decision involving the same parties and the same contractual provisions (Transport Costs decision). As the proceedings were not consolidated, separate reasons for each matter, CC 1447/2009 and CC 1442/2009, have been published. The adjudication applications were dismissed as the adjudicator determined they were made out of time. The applications were not determined on their merits.

 

Spotters Cost decision: background and submissions

 

9 The applicant (Longmont) and the respondent (Fleetwood) entered into a contract to construct the Worsley Efficiency & Growth Camp Accommodation (project) in Collie in or about April 2008 (contract). Longmont is referred to in the contract as the contractor and Fleetwood is referred to as the company

 

10 There is no dispute between the parties that the contract is a construction contract as defined in the CC Act.

 

11 Longmont claims a dispute arose with Fleetwood in respect to a payment claim made for Spotters Costs dated 4 May 2009, being invoice No 90501 for the amount of $63,195.25 plus GST. Longmont made application for adjudication on 28 July 2009.

 

12 Both the Transport Costs decision and the Spotters Costs decision involved interpretation of Special Condition 15 (SC-15) in the contract.

 

13 The terms of SC-15 that were before the adjudicator were as follows:

 

15.1 CONTRACTOR shall prepare and submit invoices as follows:

 

(a) CONTRACTOR shall submit estimates of Work performed and projected for performance during that month by the 20th of each month, and

 

(b) COMPANY shall review the estimates with CONTACTOR and upon approval shall return them for submittal with CONTRACTOR'S invoice on the 1st of the following month.

 

CONTRACTOR shall certify in each invoice that (a) there are no known liens against the Project or COMPANY'S property arising from or related to the Work and (b) that all of the CONTRACTOR'S due and payable bills related to the Work have been paid or are included in the application for payment.

 

Within 30 days after receipt of a correct invoice, COMPANY will pay the approved invoice amount.

 

14 During the hearing before this Tribunal, Fleetwood argued that the form of SC-15 in the executed contract between the parties was different and did not state that within 30 days after receipt of the correct invoice, the company would pay the approved invoice. Fleetwood maintained, therefore, that the Tribunal should have regard to this different version of the contract. For the reasons that follow later, there is no need to set out details of this different version of SC-15.

 

15 The adjudicator found that as the contract was silent as to what was to occur in the event that Longmont's invoice of 5 May 2009 was not assessed as 'correct', pursuant to SC-15, then the provisions of cl 7 Sch 1 Div 5 of the CC Act were to be implied.

 

16 The adjudicator then went on to find that the payment dispute arose 28 days after 20 May 2009, being 17 June 2009. The significance of 20 May 2009 is that the adjudicator considered that was the first day on which Fleetwood was obliged under the contract to consider the claim. He, therefore, found that the latest date for service of the application for adjudication was 28 days after 17 June 2009, being 15 July 2009. As the adjudication application was served on 28 July 2009, it was dismissed for being out of time.

 

17 Longmont contends that the adjudicator has wrongly implied the terms at Sch 1 Div 5 cl 7(3) of the CC Act and maintains that SC-15 provided their invoice be paid within 30 days.

 

18 Additionally, Longmont argues that as their invoice of 4 May 2009 was not to be approved under SC-15 until the end of the month of May, the Spotters Costs claim was due for payment by Fleetwood on or before 30 June 2009. Longmont maintains, therefore, that the payment dispute arose on 1 July 2009. It argues that the latest date for adjudication pursuant to s 26 of the CC Act was 29 July 2009. As their application was made by 28 July 2009, Longmont maintains their application was within time.

 

19 As previously stated, Fleetwood argue that the adjudicator did not have regard to the correct version of SC-15.

 

20 Alternatively, based on the version of SC-15 before the adjudicator, Fleetwood submits that it is wrong to characterise the invoice of 4 May 2009 as an estimate of work performed and projected performance during the month of May, as that invoice is simply a claim for work done in the previous month of April 2009. We do not understand Longmont to dispute this. The invoice states: 'Use of Spotters at Worsley, April 2009'.

 

21 Fleetwood submits that the mechanisms under SC-15 do not apply to an invoice which has not been approved, and the adjudicator was correct to imply the provisions under Sch 1 Div 5 cl 7 of the CC Act.

 

The relevant statutory provisions

 

22 The regime under the CC Act requires an adjudicator to dismiss an application without making a determination of the merits on a number of stated grounds, which include the application not having been served in accordance with s 26 of the CC Act.

 

23 Section 26(1), relevantly, provides that to apply for an adjudication application, the party must apply within 28 days after a dispute arises:

 

24 Section 6 of the CC Act provides, when a payment dispute arises, as follows:

 

For the purposes of this Act, a payment dispute arises if -

 

(a) by the time when the amount claimed in a payment claim is due to be paid under the contract, the amount has not been paid in full, or the claim has been rejected or wholly or partly disputed; …

 

25 Section 3 of the CC Act defines payment claim as follows:

 

payment claim means a claim made under a construction contract –

 

(a) by the contractor to the principal for payment of an amount in relation to the performance by the contractor of its obligations under the contract; or

 

(b) by the principal to the contractor for payment of an amount in relation to the performance or non-performance by the contractor of its obligations under the contract;

 

26 Section 16, s 17 and s 18 of the CC Act set out when terms will be implied into a construction contract. Those sections provide as follows:

 

16. Making claims for payment

 

The provisions in Schedule 1 Division 4 are implied in a construction contract that does not have a written provision about how a party is to make a claim to another party for payment.

 

17. Responding to claims for payment

 

The provisions in Schedule 1 Division 5 about when and how a party is to respond to a claim for payment made by another party are implied in a construction contract that does not have a written provision about that matter.

 

18. Time for payment

 

The provisions in Schedule 1 Division 5 about the time by when a payment must be made are implied in a construction contract that does not have a written provision about that matter.

 

27 Clause 7(3) of Sch 1 Div 5 of the CC Act follows:

 

(3) Within 28 days after a party receives a payment claim, the party must do one of the following, unless the claim has been rejected or wholly disputed in accordance with subclause (1) -

 

(a) pay the part of the amount of the claim that is not disputed;

 

(b) pay the whole of the amount of the claim.

 

Consideration

 

28 For the same reasons expressed at paras [27] - [30] in the Transport Costs decision, the Tribunal does not consider it appropriate to determine this matter, other than by reference to the version of SC-15 that was before the adjudicator at the time of the adjudication.

 

29 As in the Transport Costs decision, determination of this matter turns on the meaning and effect of SC-15. We therefore adopt the same reasoning expressed in the Transport Costs decision, and set out here for ease of reference:

 

Although SC-15 at first glance suggests a time limit within which payment must be made, the mechanism for payment in SC-15 is dependent on an approved invoice being submitted. SC-15 requires Longmont to submit estimates of work performed and projected for performance during that month by the 20th day of each month.

 

Once such an estimate is provided, Fleetwood is to review the estimates and, upon approval, return them for submittal by Longmont on the 1st of the following month.

 

It is only following that process that SC-15 provides for payment to be made 30 days after receipt of an approved invoice.

 

A similar, although in some respects significantly different, clause was the subject of consideration in Blackadder Scaffolding Services (Aust) Pty Ltd and Mirvac Homes (WA) Pty Ltd [2009] WASAT 133 ( Blackadder ). The issue of when and how a response to a payment claim is to be made was discussed in Blackadder .

 

The Tribunal found that as the clause did not contain the method of how and when to respond to a payment claim, it was necessary, pursuant to s 17 and s 18 of the CC Act , to imply the terms set out in Sch 1 Div 5 cl 7(3) of the CC Act. At [42] of Blackadder , the Tribunal stated:

 

It is clear that it was Parliament's intention that the contract should itself stipulate both when a response to a payment claim is to be made, and how to respond, failing which the provisions in the schedule about 'that matter' will be implied. ...

 

We do not consider that, in this case, SC-15 stipulates how a payment claim is to be made. Longmont argues that the payment claim was made when it issued its invoice dated 31 May 2009.

 

SC-15 simply refers to Longmont submitting estimates of work performed, and estimated to be performed, during that particular month. It then refers to a system by which Fleetwood reviews that estimate. In Blackadder , the relevant contractual provision referred to submitting a 'Provisional Progress Claim'. In this case, SC-15 speaks not in terms of the making of a payment claim, but refers to the submission of an estimate of work performed and projected for performance for approval. A payment claim under s 3 of the CC Act is a claim for payment of an amount in relation to the performance by the contractor of its obligations under the contract. It is not a claim for payment in relation to the estimated performance by the contractor under the contract.

 

Further, SC-15 only allows payment upon an approved invoice.

 

It remains silent as to the process to be employed when an invoice is not an approved invoice.

 

So, although SC-15 stipulates a time within which payment of an approved invoice is to be made, the provision is silent as to what is to occur should the estimate not be approved or where no response to an estimate is given.

 

In our view, in the context of the CC Act read as a whole, the references in s 16, s 17 and s 18 thereof to making a claim for payment, or the time within which a payment must be made, must be read as being a reference to a payment claim within the meaning of s 3 of the CC Act. Therefore, we do not consider that SC-15 is a written provision which provides a mechanism for making or responding to a payment claim. Despite SC-15 referring to a time within which payment is to be made, the provision for when payment is to be made has no application because it does not relate to a payment claim as defined in s 3 of the CC Act. We find for the above reasons that the provisions in Sch 1 Div 4 referred to in s 16, s 17 and s 18 of the CC Act are implied into the contract.

 

If we are wrong in that conclusion, a provision which allows a claim to be made only for, and obliges a contractor only to pay within a stated timeframe, an approved amount, in our view, is a provision which purports to modify or restrict the operation of the CC Act, and, as such, has no effect by virtue of s 53 of the CC Act.

 

Therefore, on either of the above bases, s 16, s 17 and s 18 of the CC Act apply, and as no payment claim was ever made, no payment dispute ever arose and, consequently, the adjudication application was not made within 28 days of a payment dispute arising.

 

30 The adjudicator treated Longmont's invoice of 4 May 2009 as a payment claim, but found that as there was no provision for disputing an invoice which had not been approved, the provisions of Sch 1 Div 5 cl 7 of the CC Act were implied into the contract. The adjudicator on a basis we do not follow found that the payment dispute arose on 17 June 2009 and that the adjudication application had to be lodged by 15 July 2009.

 

31 The decision of the adjudicator to the effect that the application was out of time is therefore correct, although we have arrived at that conclusion for different reasons. The application to review the decision must therefore be dismissed and the decision affirmed.

 

Orders

1. The application to review the adjudicator's decision of 24 August 2009 in adjudication No 04-09-12 is dismissed.

 

2. The decision of the adjudicator made on 24 August 2009 in adjudication No 04-09-12 is affirmed.

 

I certify that this and the preceding [31] paragraphs comprise the reasons for decision of the State Administrative Tribunal.

___________________________________

MR C RAYMOND, SENIOR MEMBER