RJ Neller Building Pty Ltd v. Ainsworth [2008] QDC 129 (25 June 2008)

 

Last Updated: 26 June 2008

 

DISTRICT COURT OF QUEENSLAND

 

CITATION:

RJ Neller Building Pty Ltd v Ainsworth [2008] QDC 129

PARTIES:

RJ NELLER BUILDING PTY LTD

Plaintiff/Respondent

v

KJERULF DAVID AINSWORTH

Defendant/Applicant

FILE NO:

95 of 2007

DIVISION:

Civil

PROCEEDING:

Application

ORIGINATING COURT:

District Court, Maroochydore

DELIVERED ON:

25 June 2008

DELIVERED AT:

Maroochydore

HEARING DATE:

23 May 2008

JUDGE:

K S Dodds, DCJ

ORDER:

The application is refused with costs.

CATCHWORDS:

BUILDING CONTRACTS – RESOLUTION OF DISPUTES – ADJUDICATION – where respondent to adjudication brought proceeding in District Court arising out of same contract as adjudication – where proceeding in District Court brought after adjudicators certificate served on respondent to adjudication but before adjudicators certificate filed in District Court – whether enforcement warrant issued upon judgment in District Court on filing of adjudication certificate should be stayed

 

Building and Construction Industry Payments Act 2004 (Qld) s 31 , s 100

 

Uniform Civil Procedure Rules r 667, r 791

 

Building and Construction Industry Security of Payment Act 1999 (NSW)

 

Cases cited:

Brodyn Pty Ltd v Davenport & Anor (2004) NSWCA 394

COUNSEL:

L C Alford for the plaintiff/respondent

P W Hackett for the defendant/applicant

SOLICITORS:

Ray Barber for the plaintiff/respondent

Morgan Conley Solicitors for the defendant/applicant

 

[1] This application by Kjerulf David Ainsworth sought:

 

A declaration:

 

 

Orders:

 

[2] At the hearing, counsel for the applicant proposed that orders be made staying the enforcement warrant, granting liberty to apply and that the costs of the application be part of the parties costs in proceeding 1247 of 2007 upon the applicant’s undertaking not to encumber transfer assign or otherwise deal with certain real property upon which the respondent had performed building or construction work so as to reduce his equity therein below $150,000 pending final determination of proceeding 1247 of 2007.

 

Proceeding BD1247 of 2007

 

[3] On 2 May 2007 Ainsworth filed a claim and statement of claim in the District Court at Brisbane. The claim sought:

 

Declarations:

 

 

Orders:

 

The Adjudication

 

[4] Neller was a registered builder. On 31 October 2005 a minor works contract was entered into by Neller and Ainsworth for alterations to a residential property owned by Ainsworth at Noosa Heads (the property). Neller and its subcontractors performed work on the property from October 2005 to 12 December 2006 when they were locked out of the property. On 26 February 2007 Neller issued a payment claim for progress payment under section 17 of the Act for $59,907.09. On 28 February 2007 Ainsworth provided a payment schedule pursuant to section 18 of the Act indicating he proposed to pay nil. As required by section 18 reasons were included viz:

 

 

[5] The adjudicator addressed each of Ainsworth’s reasons set out in the payment schedule. He reduced the amount claimed by refusing a 20% margin on variations to the contract. Additionally although not included in Ainsworth’s reasons for refusal in his payment schedule, he considered a contention by Ainsworth in submissions in response to Neller’s submissions at the adjudication that he intended to live in the property. Section 3(2)(b) of the Act has the effect that the Act does not apply to a construction contract for carrying out domestic building work if a resident owner is a party to the contract to the extent the contract relates to a building or part of a building where the resident owner intends to reside. He noted that the written contract between the parties in item 1 stated that the owner of the property was not the resident owner. He concluded he was not satisfied the provisions of the Act exempting resident owners from its application applied to Ainsworth. He concluded Neller was entitled to a progress payment of $50,771.74.

 

The Enforcement Warrant

 

[6] The adjudicator’s decision was given on 28 March 2007. On 30 April 2007 the adjudicator’s certificate was served on the plaintiff with a demand for payment. On 2 May 2007 Ainsworth filed the claim and statement of claim earlier referred to. On 3 May 2007, Neller filed the adjudicator’s certificate in the District Court at Maroochydore. By this action the certificate operated as a judgment in favour of Neller against Ainsworth for $55,644.13 ($1,022.39 for interest and $3850 for costs was included). On 6 March 2008 Neller sought and obtained an enforcement warrant from the District Court at Maroochydore.

 

The Act

 

[7] The plaintiff was entitled to bring civil proceedings against the first defendant arising out of the contract. The adjudication proceeding does not effect those proceedings except that the court hearing those proceedings must make allowances for it in any orders it makes in those proceedings.

 

[8] Where, as here, the filing of the adjudicator’s certificate had resulted in a judgment for a debt enforceable in the District Court, the Act provides a proceeding may be brought to have the judgment set side. In any such proceeding the applicant is not entitled to bring any counterclaim against the claimant, to raise any defence in relation to matters arising under the construction contract, to challenge the adjudicators decision and is required to pay into court as security the unpaid portion of the adjudicated amount pending the final decision in those proceedings

 

[9] The object of the Act is “to ensure that a person is entitled to receive and is able to recover progress payments” if the person undertakes to carry out construction work under a contract or to supply related goods and services under a construction contract.

 

[10] Section 8 of the Act provides that “the object is to be achieved by-----

 

(b) establishing a procedure that involves---

(i) the making of a payment claim by the person claiming payment; and

(ii) the provision of a payment schedule by the person by whom payment is payable; and

(iii) the referral of a disputed claim or a claim that is not paid to an arbitrator; and

(iv) the payment of the progress payment decided by the adjudicator”.

 

[11] The explanatory notes to the Bill which became the Act describe the objective of the legislation as entitling certain persons who carry out construction work or who supply related goods and services, to a timely payment for the work they carry out and the goods and services they supply. A reason for the bill was that common law and contract law remedies were not sufficient to address security of payment issues. The construction industry was particularly vulnerable to security of payment issues. “The failure of any one party in the contractual chain to honour its obligations can cause a domino effect on other parties resulting in restricted cash flow, and in come cases, insolvency.

 

[12] The Bill establishes a statutory based system of rapid adjudication for the interim resolution of payment on account disputes involving building and construction work contracts.

 

[13] Rapid adjudication will be conducted by an independent arbitrator with relevant expertise. If the decision of the adjudicator is in whole or in part in favour of the applicant, the respondent is required to pay the specified amount directed by the adjudication to the applicant-----

 

[14] Rapid adjudication does not extinguish a party’s ordinary contractual rights to obtain a final resolution of a payment dispute by a court or tribunal of competent jurisdiction”.

 

[15] The Act is in similar terms to the Building and Construction Industry Security of Payment Act 1999 (NSW) . In Brodyn Pty Ltd v Davenport & Anor (2004) NSWCA 394 at 440-1, paragraph 51 the New South Wales Court of Appeal in a unanimous judgment considered the Act disclosed a legislative intention to give an entitlement to progress payments. It provided “a mechanism to ensure that disputes concerning the amount of such payments are resolved with a minimum of delay. The payments themselves are only payments on account of a liability that will be finally determined otherwise: sections 3(4) and 32. The procedure contemplates a minimum of opportunity for court involvement: sections 3(3) and 25(4). The remedy provided by section 27 can only work if a claimant can be confident of the protection given by section 27(3) if the claimant faced the prospect that an adjudication determination could be set aside on any ground involving doubtful questions of law, as well as of fact, the risks involved in acting under section 27 would be prohibitive and section 27 could operate as a trap.”

 

The Statement of Claim in BD1247 of 2007

 

[16] The statement of claim in proceeding 1247/2007 refers to the contract for Neller to undertake renovation and construction work on the property owned by Ainsworth. It asserts Ainsworth was a resident owner of the property within the meaning of the Acts. It claimed that Neller breached the contract by:

 

 

[17] It claimed that by reason of the breaches Neller was not entitled to seek any payment outside the contract and therefore wrongly issued a payment claim under the Act and sought adjudication. Further, because Ainsworth was a resident owner in terms of the Act, Neller was not entitled to payment for any additional works which may have been undertaken, the adjudicator had no jurisdiction to issue his adjudication and the adjudication decision was invalid.

 

[18] Neller responded to the claim with a defence and counterclaim. The counterclaim sought that the adjudication and the amount found due by the adjudicator be upheld.

 

Decision

 

[19] The relief sought by Ainsworth requires the exercise of the courts discretion in his favour. In that regard it is submitted he is a person of substance with a substantial equity in the property at the centre of the dispute and will undertake not to diminish that equity below $150,000 whereas Neller is a $2 private company registered since 2001 operating an overdraft secured over real property where the security is not provided by it and with a charge registered over its assets and undertakings. Although the principal, Mr Neller may be a registered builder for many years with a relatively large annual turnover, there is a risk that if ultimately successful in 1247 of 2007, Ainsworth may not recover the adjudicated amount from Neller if it is paid to Neller now.

 

[20] No doubt execution of a judgment upon an adjudication under the Act could in an appropriate case be stayed even though the policy of the Act is for progress payments with a minimum of delay and court involvement. The party seeking the stay however has the task of persuading the court of discretionary factors in favour of that course sufficient to overcome the policy of the Act.

 

[21] I am not persuaded Ainsworth has done so. I am simply asked to infer that if Ainsworth is successful in 1247 of 2007 he may not recover the paid over adjudicated amount. Nothing other than that mentioned above to support that inference has been provided.

 

[22] On the other hand, a stay of the judgment based upon the adjudication will defeat the plain policy of the Act.

 

[23] The application is refused with costs.