Bell v Pearce (Home Building) [2006] NSWCTTT 274 (19 May 2006)

 

CONSUMER, TRADER AND TENANCY TRIBUNAL

Home Building Division

 

 

 

APPLICATION NOS:

 

HB03/52669 and HB04/09980

 

OWNERS:

 

Graham Phillip Bell and Narelle Joyce Bell

 

BUILDER:

 

Christopher James Pearce

 

APPLICATION:

 

Final orders

 

HEARING:

 

28 April 2006 at Newcastle

 

APPEARANCES:

 

Owners in person; Mr C Doyle, solicitor, for the Builder

 

LEGISLATION:

 

Home Building Act 1989

Building and Construction Industry Security of Payment Act 1999 (BCISP Act)

Consumer, Trader and Tenancy Tribunal Act 2001

 

CASES:

 

Brodyn Pty Limited v Davenport [2004] NSWCA 394

Hungerfords v Walker (1989) 171 CLR 125

 

 

 

Pursuant to Section 50 of the Consumer, Trader and Tenancy Tribunal Act 2001, orders published on 19 May 2006 are amended as follows:

 

ORDER

 

The Tribunal orders that:

 

  1. The Owners Graham Phillip Bell and Narelle Joyce Bell are to pay Christopher James Pearce $37,669.99 immediately; and

 

  1. The parties are to file and serve any submissions as to costs on or before 1 July 2006, for a determination of the award of costs on the papers.


REASONS FOR DECISION

 

 

APPLICATION

 

  1. I gave reasons for decision on the applications for principal relief as long ago as 23 June 2005. I had heard evidence just over 3 months before then, but the decision had awaited the receipt of submissions by the parties. Some aspects of the case had been argued before one of my colleagues, and not before me. There were some other matters, such as interest, about which I had been given no submissions by either party. Accordingly, I directed that the parties calculate these amounts and that in default of their agreeing the sums, each had leave to seek a further short hearing to resolve outstanding questions.

 

  1. There was then an application by the solicitor for the Builder to re-open the hearing to “reconsider” the aspect of termination of the contract, which I had covered in paragraphs 26 to 28 of the first decision. I refused that leave, giving reasons on 26 October 2005.

 

  1. Given the relationship between the parties, they were unable to reach the agreement I had suggested in my first decision and so the resolution of these final questions fell to me. It was necessary to give some directions to prepare the matter for hearing these questions. I heard oral submissions on 28 April 2006, supplementing the written material previously exchanged. As before, I have been made aware of some without prejudice material between the parties; I have again ignored that in reaching my decision.

 

APPEARANCES

 

  1. The amounts in dispute exceeded $25,000.00 and thus the parties were entitled to be represented. I understand that the previous Member gave the necessary leave some time ago. Mr Doyle appeared for the Builder pursuant to that leave, as he had done on some past occasions. The Owners continued to be unrepresented.

 

JURISDICTION

 

  1. The proceedings arise from the construction by the Builder for the Owners of a pair of semis at “…” Nelson Bay. There is a claim by the Builder for a progress payment and by the Owners for damages for breach of warranty. The disputes are therefore home building disputes and the Tribunal has jurisdiction under rhe provisions of the Home Building Act 1989 s.48K. Neither party has suggested otherwise.

 

FINDINGS

 

  1. Before the matter came to the Tribunal, there had been an adjudication by Victor Lin under the provisions of the Building and Construction Industry Security of Payment Act 1999, on an application by the Builder. It may well be that there was no jurisdiction for Mr Lin to make that adjudication (see s.7 of that Act), but that is not a question which I empowered to determine. While the determination stands, I must accept it as valid (see Brodyn Pty Limited v Davenport [2004] NSWCA 394) and also accept that the findings set out in that adjudication operate to create estoppels between the parties. In my first decision I found that the parties were therefore bound by the finding by Mr Lin that the contract was terminated on or about 29 March 2004.

  1. Mr Doyle drew issue with that finding and asked that it be revisited. My decision of 26 October 2006 covered his request. As a part of his submissions now before me, Mr Doyle again submits that I should revisit my decision. For the reasons given on 26 October 2005, I decline to do so. Beyond the matters set out above, the evidence makes it clear that after that date the parties treated the contract as having reached its end. Mr Pearce did return to the site, but as project manager/carpenter, and not as a builder.

 

  1. I do take into account as required by BCISP Act s.32 the evidence now before me that the adjudication sought by the Builder was dismissed because it was made out of time. Thus the sum is nil.

 

  1. The first submission which Mr Doyle makes is that I should revisit my first decision under the provisions of the Consumer, Trader and Tenancy Tribunal Act 2001 s.50 (a slip rule provision) and reconsider the date upon which the Builder should have completed the works. His submission was that as there had been no final orders pronounced, this matter was not final and thus open to be revisited. The Owners opposed this and said that the Builder was bound by the findings previously made.

 

  1. In my opinion, the proper approach to this matter is that I left the final calculations to the parties; they have failed to reach agreement on those figures. At the hearing before me on 22 March 2005, neither the Builder nor the Owners drew my attention to the provisions of Clause 9.1 of the contract and a deemed extension of time for completion for the 5 weeks’ industry break over Christmas. It was not an extension for which notice was required. Accordingly the claim for liquidated damages is reduced by $110.00 each day for the 22 working days by which the contract was extended pursuant to that clause. That reduces the number of days for which the Owners are entitled to liquidated damages to 85, and thus the sum will be adjusted to $9,350.00.

 

  1. I consider that the Owners bear the burden of proof on the matters which have taken the bulk of the time. It is they who assert that they incurred costs in completion of works and rectification of defects. During the course of the hearing on 28 April 2006, Mr Doyle conceded that the Owners had paid $500.00 in cash for completion costs for which they had no receipts. The parties were also agreed on the final contract sum which needed to be adjusted, and the method of justification – issues about which the Builder would have borne the burden.

 

  1. I now turn to examine the particular claims by the Owners, using the paragraph numbers in their submission of 17 March 2006. I start from the finding made earlier that after the termination of the contract the Builder went back and did further work (para 28). The matters in dispute on the Owners’ side are claims for completion of the works and are made under the provisions of Clause 36.4 of the contract. The parties are agreed with the mathematical calculation set out in the Owners’ submission of 17 March 2006, and I take that as the starting point.

 

  1. The first of these items is the claim in paras 19 to 23 for work carried out by Mr Bell himself. It is claimed that using the Builder’s hourly rate this amount to $3,281.25 for the 87.5 hours involved. There are several problems with this claim. I do not know how many hours a competent builder would have taken to carry out this work. It may well have been less than the 87.5 hours taken by Mr Bell. It may have been less. There is nothing to assist me on the evidence. Mr Bell did not give any evidence that he had foregone other income in order to carry out the work. I do not propose to allow this claim.

 

  1. Paras 24 to 28 deal with claims for defective work. Paras 14 to 18 deal with items claimed for completion costs beyond those set out above. The Builder has replied. The lists in the schedule are extensive, and many deal with very small amounts, some so low that I would have thought that the parties could agree upon them. They have not. I propose to deal with them in a brief manner, proportionate to the sums involved.

Owners’ claim for defective work

Builder’s response

Tribunal finding

Sum allowed

Garage door – said to need realignment

Responsibility of subcontractor to return and rectify

Subcontractor did not return, and Builder responsible to the Owners for work carried out by his subcontractor

88.00

Angle joint defective at raked ceiling

No invoice supplied and unable to determine if defective

No invoice with submissions; unable to determine

0.00

Repaint ceiling after above item carried out

Unable to determine if base item required

As above

0.00

Seal and repair courtyard and balcony ceilings

No documentation to support claim

No documents to verify claim or amount paid

0.00

Engineering certificates – a certificate not supplied at proper stage then work covered up.

Sum is excessive, should only be about $250.00 and would have been less had original engineer been retained.

Certification not carried out at proper stage, need to carry out some extra works to provide proper certificates, sum appears large, but unable to say excessive on this evidence

902.00

Postage to pay contractors

No verification

Included in the $500.00 conceded

0.00

Move and level sand

Conceded in full

Allow

200.00

Fit removable hinges wc doors

Conceded in full

Allow

77.00

Perimeter post spray

Conceded in full

Allow

290.40

Modify wc doors by providing cover strip etc

Duplication of above; no invoice provided

Allowed, as required by Council, but covered by concession in relation to unverified items

0.00

Occupancy Certificate as builder was required to pay for all necessary inspections

Attending to provision of this certificate was not the Builder’s contractual responsibility

Not the builder’s contractual responsibility; provision of inspections does not require Builder to pay for final certificate

0.00

Repairs to front door lock which failed 1 month after completion

Unable to determine if defective or warranty work; locks working at time Builder was on site

Ultimately irrelevant if defective work or warranty item, but probably the latter; in either event it is the Builder’s responsibility to the Owners

79.75

Repair bath spout containing a faulty part

Spout provided by owners

Owners liable for items they provided

0.00

Fitting astragals to council requirements

No invoice or receipt for item and unable to determine if defective or warranty item

Builder required to build to council requirements, but amount included in the $500.00 conceded where no invoice

0.00

 

 

Total

$ 1637.15

 

 

 

 

Owners’ claims for completion costs

Builder’s reply

Tribunal finding

Sum allowed

Tiling not completed, as shown in photographs

Tiling was completed

Photographs show some outstanding tiling. Sum claimed seems reasonable

990.00

Bathroom cornices not fitted and set at termination, but unable to locate invoice

No particulars of claim to enable any submission

Unable to verify claim

0.00

Balcony tiling

Conceded

Conceded

1,947.00

Internal painting

Conceded

Conceded

5,500.00

External painting

Conceded

Conceded

4,400.00

Steelwork for carport is doubled claimed by Builder following allowance of claim as a variation and included in contract sum

Allowed in the decision of 23 June 2005, and not a doubling up

Not a doubling up, and should not be allowed against the Builder

0.00

Letterboxes should have been built in and were not. No invoice

No invoice

No verification and included in the concession of $500.00 for unverified items

0.00

Door furniture etc admitted into evidence by the Tribunal on 13 March 2005

Refers to external furniture and says that the claimed items are not those specified in the contract

Claim is for all door furniture, not limited to external. Sum claimed is reasonable, and allowed

2,133.30

Builder’s clean-up for Unit A

Conceded

Conceded

200.00

Hire of industrial vacuum

Conceded

Conceded

48.17

Builder’s clean-up for Unit B where said that only part of Unit A was cleaned

Queries why the sum is more than double the costs of cleaning Unit A

Greater work required than for Unit A. Sum is reasonable and allow in full

480.00

Acrylic block

Conceded in full

Conceded in full

1,865.00

Flyscreens

Conceded in full

Conceded in full

1,809.50

Railings and balustrades not included in PC items, and shown on plans

Those supplied not those shown on plans and sum claimed is excessive

Unable to read invoice in any detail. Items for part of contract works, and should be allowed in principle. Unable to say that sum claimed is correct. Parties to agree

0.00

Side stairs shown on contract drawings and therefore form part of works

Not within scope and therefore could only have been a variation

Shown on plans and form part of works; allow as claimed, as works carried out cheaper than contract works would have been

1.353.00

Letterbox units as shown in contract plans

Not part of contract or PC, would be a variation

The letterboxes are shown on plans as to be as selected by Owners. Could not form part of contract on that basis

0.00

Hardware etc required to carry out minor repairs

Rectification the responsibility of painter

Disallowed for reasons set out in para l above

0.00

Paint roller cover

Would have been provided by contracted painter as part of his work

Agree with Builder. Claim is specious

0.00

Black plastic to protect work surface when overnight showers predicted

Not originally detailed to the Builder, and no real submission

Protection of work for incoming trades is a necessary part of building work. Allow

26.00

Renderer

Conceded in full

Conceded in full

1,500.00

Waterproofer

Conceded in full

Conceded in full

1,100.00

Tip fees

Conceded in full

Conceded in full

32.00

Misc items of hardware purchased to enable completion

No verification

No verification, but covered in the $500.00 concession

0.00

Backfilling over services beyond landscaping

Part of landscaping

In principle, this is an item for which the Builder is liable as a normal incident of building; the claim is excessive for what would be required and there appears to be considerable overlap with landscaping. Allow only in part

250.00

Cleaning materials used by Owners for part cleaning of Unit A

Covered by Impress Cleaners invoice at item 4.09

Minor item but allow the principle

11.70

Telephone outlets etc

Conceded in full

Conceded in full

75.35

Stormwater fitting to connect PVC downpipe to stormwater pipe

Not able to agree within contract

Would be an incidental item to carrying out what are clearly contract works, and satisfied that would have itself been such an item

6.55

Garage door controls

Conceded in full

Conceded in full

220.00

Door furniture not otherwise covered

Conceded in full

Conceded in full

75.15

 

 

Total

$ 24,022. 42

 

 

 

 

Owners’ claims for labour

Builder’s response

Tribunal finding

Allowance

Painting rectification

Responsibility of contractor

Not allowed – see para o

0.00

Fitting hanging rails to wardrobes not done by Builder

Builder returned to site to correct the incorrect fitting by Owners

Not satisfied that Owners have proven their claim

0.00

Fitting cover strips and filling gaps in kitchen

Builder returned to site to carry out this work

Not satisfied that Owners have proven their claim

0.00

Initial clean as set out in schedule

Work not properly described

Not allowed – see para o

0.00

Fit and seal spa pump covers

Conceded in full

Conceded in full

18.75

Install telephone outlets and conduit

Conceded in full

Conceded in full

112.50

Planning, ordering and supervision

Done by Builder when he returned as project manager

See para o above

0.00

Purchase and programme garage door controls

Excessive claim

Sum appears excessive and allow only as conceded

17.75

 

 

Total

$ 149 .00

 

 

  1. The total for the items covered above is $25,808.57.

 

  1. The Owners claimed the cost of rectification of painting work carried out by a painter whom they had engaged as part of their completion work. I do not allow this; any claim which they have is against their contractor and not the Builder.

 

  1. The Owners submit that they are entitled to the costs of retaining a lawyer whilst they were carrying out the completion work. They submit that a builder would normally carry such expenses as obtaining legal and accounting advice as a part of the contract price and that they therefore are entitled to the sum. The Builder’s submission is that the sum should form part of any costs order, and is not a cost of completion.

 

  1. I accept the submission by the Builder. The costs were incurred not as builders but as dissatisfied owners. The appropriate place to consider these is in discussion as to costs. They are not allowable as a cost of completion.

 

  1. The Owners also claim interest on the sums which they paid. The calculation is set out in their submission and for present purposes I accept the mathematics of the calculation as correct. I do not accept the principle. Their claim under Clause 36 of the contract is for cost of completion; the clause makes no provision for interest. Further, there is no evidence before me which would justify an award of interest on the principles set out in Hungerfords v Walker (1989) 171 CLR 125. I disallow the claim.

 

  1. The mathematics of the claim may be summarised:

Balance of Contract sum as agreed

73,328.56

Total allowances in favour of Owners set out above

25,808.57

Balance

47,519.99

Liquidated damages in favour of Owners

 

9,350.00

Deduction

500.00

Balance in favour of Builder

 

$37,669.99

 

 

  1. That leaves the question of costs. Mr Doyle submits that costs should follow the event. The Owners make no submissions as to costs. My present inclination is that I should order that each pay their own costs. My reasons for so doing are as follows. Each party has had some limited success in the decisions of 23 June 05 and today. The Builder failed in his application the subject of the decision of 26 October 05. The parties emerged fairly evenly balanced from the decision of Mr Isaac.

 

  1. There may be some matters – eg offers of settlement in the form of Calderbank letters – of which I am not aware, but which may impact the question of costs. The parties may disagree with my present thoughts. They therefore have leave to file and serve submissions as to costs. I shall then decide this final question on the papers.

 

 

 

G J Durie

Senior Member

Consumer, Trader and Tenancy Tribunal

 

19 May 2006

(Amended 19 September 2006)